Friday 3/27/2012


Weather Sunny 59˚/31˚

Subs on Site
Keith (DG Concrete)  (2)

Work in Progress:
Pre-Con with Lonny, Uintah County and the Fire Marshal



Keith (DG Concrete) delivered a track hoe.

Thursday 4/26/2012



Weather
 Cloudy 74˚/41˚

Subs on Site
<none>

Work in Progress:
Changed electrical Pre-Con to Monday 4/30/2012 @10:00
Went over GC's with McKay
Started AGEC getting Certification for the city

Wednesday 4/25/2012


Weather Cloudy 75˚/53˚

Subs on Site
<none>

Work in Progress:
Set up electrical Pre-Con for Wednesday, 5/2/2012 @10:00
Nick and I finalized schedule

Tuesday 4/24/2012


Weather Cloudy 80˚/54˚

Subs on Site
<DG Concrete> (1)

Work in Progress:
Met with James, Shawn, Andrew, and Jeff @ EA URBIA
   Emailed RFI's OK carbon copy all of them
   Address Jeff for Structural
   Address to Shawn for Architectural
Keith delivered a bulldozer to the site.  Road damage to Main and 2500 W
Nick and I worked on schedule

Monday 4/23/2012


Weather Cloudy 84˚/52˚

Subs on Site
<none>

Work in Progress:
Emailed Mat Jenson (Epic Engineering) for special inspection
Scheduled Meeting with James Williams and team for 8 AM tomorrow.
Went over McKay's notes on RFI's to get started on.
Got bids on Office trailers
Contacted Port-o-Pot co.'s
Talked to Aaron Eaton (Unitah County) about Pre-Con.

Friday 4/20/2012


Weather Cloudy High 69˚

Subs on Site
<none>

Work in Progress:
Estimated concrete yardage for special inpections
Left message for Mat Jenson(Epic Engineering)
Created Phase Plan
Started Pavement Plan .

Thursday 4/18/2012


Weather Wind High 64˚

Subs on Site


Work in Progress:
Visited The Renascence Inn. Idaho Falls, Idaho for training and research.

Wednesday 4/18/2012


Weather Light Rain High 59˚

Subs on Site
<none>

Work in Progress:
Plan study and prepared notes for future RFI's

Tuesday 4/17/2012

Weather Rain High 60˚

Subs on Site
Keith Gordon meeting for possible excavation.

Work in Progress:
Started imputing schedule into Microsoft Project.

Mon 4/16/12

Weather: Clear / Hi 65

Subs on Site:
None

Work in Progress:
- Working on plan review / schedule.