Tuesday 5/8/2012
Weather Cloudy 74˚/42˚
Subs on Site
<DG Concrete> (5)
Work in Progress:
Met with Gary & Mike (Bandwidth), Terri (Questar), and Travis (Uintah County Roads) about under ground.
Bandwidth wants Strata to run up to the property line with their fiber then stop. Bandwidth will then follow Rocky Mountain Power's trenches and run to each building. Bandwidth will supply all the conduit. Bandwidth requested a single large box on the building for service and 2" conduit (supplied by us) up to the roof for the future satellite location. In the unit boxes on the patio/decks they want 2 coax and 2 CAT-5 connected to a punch out box with CAT-5 and coax to each room and the TV room. Bandwidth would like all CAT-5 terminated with RJ-45 jacks
.
Nick discussed a new layout for Questar to keep them in the park strips as much as possible and also run out to Main street so Questar could have two feeds. Travis (Uintah County Roads) said there would be a $5,000 fee for cutting the pavement to access the gas line on 2500 West because it is a moratorium road.
Met with Matt (VK Custom Construction/HUD inspector) discussed the retention schedule is 10% up to 50% of the whole project is built then it drops down to 5% until we are 90% complete then it drops to 2.5% until completion. Set up HUD inspections for the first and third Wednesday of the month at 1:00 PM. Matt (HUD) needs a spread sheet of stored material with beginning value how much was used and how much remains. Matt (HUD) would like to have a print out of building progress and labor for the trades. I am to keep a log book of all progress reports and labor on site as well as the RFI and safety logs.
Posted by
Charlie Ford
Monday 5/7/2012
Weather Cloudy 68˚/40˚Subs on Site
<DG Concrete> (5)
<Legend Engineering> (1)
Work in Progress:
Jason (Legend Engineering) Shot top back of curb along the road, the corners of building 'A', and top back of curb for building 'A's parking.
DG Concrete continued to cut the road down to sub-grade and ruff cut the grading for the whole site. They also delivered a dump truck to speed up dirt moving and bring in gravel for the first track out. They are staying on site in an RV and trailer.
Posted by
Charlie Ford
Thursday 5/3/2012
Weather Cloudy 76˚/51˚
Subs on Site
<DG Concrete> (4)
<Reliance Electrical> (2)
Work in Progress:
Temp power pole set and inspected. Rocky Mountain Power will activate in 3-5 days. Rulon will bring temp cord for my trailer on Tuesday.
Trailer delivered and set-up.
Excavator continued cutting the road and doing broad site cutting. They left at 2:30
Subs on Site
<DG Concrete> (4)
<Reliance Electrical> (2)
Work in Progress:
Temp power pole set and inspected. Rocky Mountain Power will activate in 3-5 days. Rulon will bring temp cord for my trailer on Tuesday.
Trailer delivered and set-up.
Excavator continued cutting the road and doing broad site cutting. They left at 2:30
Posted by
Charlie Ford
Wednesday 5/2/2012
Weather Cloudy 75˚/47˚
Subs on Site
<DG Concrete> (4)
<Legend Engineering> (1)
Work in Progress:
Out-house on site. Delivery driver hit the fence then backed into the Track-hoe's rolling wheel.
Surveyor Jason (Legend Engineering) on site and started with center of road, sewer, and perimeter of site. He will not be back until Monday.
Water truck and the rest of silt fence delivered on site.
Sewer stub is 12" and our pipe is 8". Chris (DG concrete) and Dusty ( Maeser Water) suggest adding a manhole. Dusty (Maeser Water) said he has a cone section but we would have to supply he box. Lonny (Legend Engineering) suggested we use 12" pipe to the first manhole instead of adding a new manhole. Dusty (Maeser Water) said he was OK with that too.
Water stub is 10" our line is 8". Dusty (Maeser Water) said a reducer is OK. I will email him and get the spec on what he would allow.

Posted by
Charlie Ford
Tuesday 5/1/2012
Weather Rain then Sunny 74˚/47˚Subs on Site
Keith (DG Concrete) (4)
Work in Progress:
Set up account at Maeser Water for temp water. They will bill each month and refund the deposit at the end of the job.
Shot elevations on sewer line and reported to Lonny. Survey tomorrowGrubbed site. Started removing top soil.
Rulon (Reliance Electric) met with Mike (Strata Networks) about temporary phone.
Mrs Shaw (The Neighbor)came by and was concerned about her fence with the top soil removed. We have left 2-3 feet undisturbed away from her fence.

.
Posted by
Charlie Ford
Monday 4/30/2012
Weather Sunny 76˚/49˚
Subs on Site
Keith (DG Concrete) (3)
Work in Progress:
Pre-Con with Brandon (Maeser Water) got check for temp meter
Keith (DG Concrete) delivered a front end loader.
Subs on Site
Keith (DG Concrete) (3)
Work in Progress:
Pre-Con with Brandon (Maeser Water) got check for temp meter
Keith (DG Concrete) delivered a front end loader.
Posted by
Charlie Ford
Friday 3/27/2012
Weather Sunny 59˚/31˚Subs on Site
Keith (DG Concrete) (2)
Work in Progress:
Pre-Con with Lonny, Uintah County and the Fire Marshal
Keith (DG Concrete) delivered a track hoe.
Posted by
Charlie Ford
Thursday 4/26/2012
Weather Cloudy 74˚/41˚
Subs on Site
<none>
Work in Progress:
Changed electrical Pre-Con to Monday 4/30/2012 @10:00
Went over GC's with McKay
Started AGEC getting Certification for the city
Posted by
Charlie Ford
Wednesday 4/25/2012
Weather Cloudy 75˚/53˚
Subs on Site
<none>
Work in Progress:
Set up electrical Pre-Con for Wednesday, 5/2/2012 @10:00
Nick and I finalized schedule
Posted by
Charlie Ford
Tuesday 4/24/2012
Weather Cloudy 80˚/54˚
Subs on Site
<DG Concrete> (1)
Work in Progress:
Met with James, Shawn, Andrew, and Jeff @ EA URBIA
Emailed RFI's OK carbon copy all of them
Address Jeff for Structural
Address to Shawn for Architectural
Keith delivered a bulldozer to the site. Road damage to Main and 2500 W
Nick and I worked on schedule
Posted by
Charlie Ford