Wednesday 5/2/2012


 Weather Cloudy 75˚/47˚

Subs on Site
<DG Concrete> (4)
<Legend Engineering> (1)

Work in Progress:
Out-house on site.  Delivery driver hit the fence then backed into the Track-hoe's rolling wheel.
Surveyor Jason (Legend Engineering) on site and started with center of road, sewer, and perimeter of site.  He will not be back until Monday.
Water truck and the rest of silt fence delivered on site.
Sewer stub is 12" and our pipe is 8".  Chris (DG concrete) and Dusty ( Maeser Water) suggest adding a manhole.  Dusty (Maeser Water) said he has a cone section but we would have to supply he box.  Lonny (Legend Engineering) suggested we use 12" pipe to the first manhole instead of adding a new manhole.  Dusty (Maeser Water) said he was OK with that too.
Water stub is 10" our line is 8".  Dusty (Maeser Water) said a reducer is OK. I will email him and get the spec on what he would allow.