Monday 5/7/2012



 Weather Cloudy 68˚/40˚

Subs on Site
<DG Concrete> (5)
<Legend Engineering> (1)

Work in Progress:
Jason (Legend Engineering) Shot top back of curb along the road, the corners of building 'A', and top back of curb for building 'A's parking.
DG Concrete continued to cut the road down to sub-grade and ruff cut the grading for the whole site.  They also delivered a dump truck to speed up dirt moving and bring in gravel for the first track out.  They are staying on site in an RV and trailer.