Tuesday 7/30/2013

Weather: Partly Cloudy 84˚/54˚

Subs on Site:
<Huskies>                        (5)
<Reliance>                       (2)

Work in Progress
(Huskies) Graded and trenched for the strip along the South end of the property.  Started planting trees and plants around Building 'B' and the Southern strip.

(Reliance) Installed the last three light poles.  One is still missing the top and another has been damaged.  They also installed the floodlights for the monument signs.

The remaining items on the temporary C of O were signed off by both the Fire Marshal and the County.  I returned the water meter to Maser.

Monday 7/29/2013

Weather: Partly Cloudy/Thunderstorm 85˚/59˚

Subs on Site:
<Huskies>                        (5)
<Warburtons>                  (1)

Work in Progress
(Huskies) Graded and trenched for the strip along the South end of the property.

(Warburtons) Collected the last of their equipment. 


Tuesday 7/23/2013

Weather: Partly Cloudy 98˚/60˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Warburtons>                  (2)

Work in Progress
(Huskies) Took delivery of 50,000 feet of sod and started installing around Building 'C'.  They should have all of the sod for the project installed this week.

(Wall to Wall) Prepped and painted the body of Building 'B&C' garages.

(Warburtons) Installed the rain gutters on Building 'A' and the Clubhouse.



Monday 7/22/2013

Weather: Partly Cloudy 97˚/60˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Warburtons>                  (2)
Work in Progress
(Huskies) Graded the strip along the South end of the property. .

(Wall to Wall) Prepped and painted the body of Building 'A' garage.

(Warburtons) Installed the rain gutters on Building 'B' and 'B' & 'C' garages.



Tuesday 7/16/2013

Weather: Partly Cloudy 93˚/67˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Reliance>                       (2)
<SBS>                              (1)

Work in Progress
(Huskies) Finished raking around the ClubHouse then planted the trees and plants.

(Wall to Wall) Painted the body on the West side of Building 'A'

(Reliance) Finished installing their trims in the ClubHouse.  We tested the ClubHouse fire panel to all of the Buildings.  One of the Exit signs would not work. 

(SBS) John Simmons came back up today to install the glass on the interior door and the self closing hinges.  He had to re key a unit where the keys did not match.  He asked that Kristie check each unit to make sure they all match.





Monday 7/15/2013

Weather: Partly Cloudy 92˚/62˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Clegg Steel>                  (3)
<SBS>                              (1)

Work in Progress
(Huskies) Raked around and installed heads for the ClubHouse. Once again someone has driven over the corners of the grass in Building 'A' parking lot.  There were also tire tracks across the North end of Building 'B' to the garage parking lot.   Also along 2500 W someone drove over the grass and many sprinkler heads.

(Wall to Wall) Painted the body on the North West corner of Building 'A'.

(Clegg Steel) Installed the last two dumpster gates and cleaned the concrete off of the stairs in each of the Buildings.  They did not get all of it cleaned up and Milo (Clegg Steel) told me that if the painters need to clean any more they can back charge them.

(SBS) John Simmons came up to install the interior glass in the ClubHouse and and change out the storage room door for the mechanical room door.  The glass he brought up was too small and he could not find the spring hinges for the storage door.  He will drive back tomorrow with the right glass.



Friday 7/12/2013

Weather: Partly Cloudy/ Light Rain 87˚/60˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (1)

Work in Progress
(Huskies) Raked around Building 'E' and set he sprinklers around Building 'B'.

(Wall to Wall) Painted the steel on the Clubhouse entry and Building 'E' entry.





Thursday 7/11/2013

Weather: Sunny  94˚/62˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (4)
<G&M Woods>                 (2)
<Red Oak>                       (2)

Work in Progress
(Huskies) Installed sod on the island against 2500 W and finished around Building 'D'.

(Wall to Wall) Sprayed the trim on Building 'A'.

(G&M Woods) Lowered the counter tops in the Clubhouse to ADA height.

(Red Oak) Reinstalled the sinks in the Clubhouse and repaired a leak in B205. 



Wednesday 7/10/2013

Weather: Sunny  100˚/62˚

Subs on Site:
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Air Doctors>                   (1)

Work in Progress
(Huskies) Installed the gravel in all the patios.  3 of them helped me pour the curb wall behind Building 'C'.

(Wall to Wall) Finished caulking Building 'A' and started masking to paint the trim.

(Air Doctors) Came to fix A207's AC. Turns out it only needed a couple of the registers closed down for better balance.

The backhoe would not drive we tried everything.  Then when I was about to give up I wiggled the clutch button( Which  has been stuck for a long while)  When it moved so did the tires.  We took the cover off and pried the button back out.


Tuesday 7/9/2013

Weather: Sunny  92˚/62˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Sterns>                          (4)

Work in Progress
(Huskies) Prepped for sod around Building 'B' and planted trees in  the island against 2500 W. 

(Wall to Wall) Building 'A' caulked and prepped.

(Sterns) Poured the last piece of sidewalk behind Building 'C'.




Thursday 7/4/2013

Weather: Partly Cloudy  86˚/63˚

Subs on Site
<Huskies>                        (5)
<Reliance>                       (2)

Work in Progress
(Huskies) Received their sod for the planter against 2500 W and the buildings. 

(Reliance) Worked on odds and ends in the Clubhouse.  Set the light poles outside of the Clubhouse.

Mario cut the control joints into the curb and gutter for Building 'B'.  Then he backfilled for the asphalt patch. 

Wednesday 7/3/2013

Weather: Partly Cloudy  94˚/62˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (2)
<Reliance>                       (2)

Work in Progress
(Huskies) Used our backhoe to regrade the pad Mario had to make for the painters and rain gutter guys lift on the East end of Building 'C' for final grade. 

(Wall to Wall) Finished painting the steel on Building 'B' and touched up the steel on 'E'.

(Reliance) Trimed out the Clubhouse.  They worked on moving the fire panel to the Clubhouse.  The phone line had not been transferred to the Clubhouse from Building 'A'.  I called Strata and put in an emergency call for no dial tone.  The service tech came out and told Nate (Reliance) that the soonest they could get dial tone would be Friday, due to the holiday.  I called the main office and talked to Valerie,  she checked and told me the same thing.  I called Kristie and warned her that the fire alarm would not call the fire department.  I also called the Marshal and told him. 

We poured the curb and gutter for Building 'B'.  We split it into 2 pours and added retardant but we still had to steal a landscaper to help finish it so we would not loose it. 




Tuesday 7/2/2013

Weather: Partly Cloudy  97˚/67˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Reliance>                       (2)
<SBS>                              (1)

Work in Progress
(Huskies) Raked around Building 'C' for final grade. 

(Wall to Wall) Stripped the masking on Building 'B' and started painting the steel on the West side.

(Reliance) Trimed out the Clubhouse.  They worked on moving the fire panel to the Clubhouse.

(SBS) Worked on the punch list for the buildings.

Mario and Juan formed for tomorrows curb and gutter pour.  They added road base and we borrowed DG's jumpping jack to compact it.





Monday 7/1/2013

Weather: Partly Cloudy  100˚/67˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Reliance>                       (5)
<SBS>                              (1)
<Sterns>                           (6)

Work in Progress
(Huskies) Hooked up their sprinklers around Building 'B' 

(Wall to Wall) Sprayed the body on Building 'B'.

(Reliance) Trimed out the Clubhouse.

(SBS) Installed the base board and some trim on the Clubhouse.

(Sterns) Poured the first half of the sidewalk behind building 'C'.

Mario dug out the curb and gutter that we need to repour.




.

Friday 6/28/2013

Weather: Partly Cloudy  96˚/60˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)

Work in Progress
(Huskies) Planted sod around Building 'D'.  

(Wall to Wall) Masked Building 'B' trim and painted the trim on the Clubhouse.



.