Tuesday 7/2/2013

Weather: Partly Cloudy  97˚/67˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Reliance>                       (2)
<SBS>                              (1)

Work in Progress
(Huskies) Raked around Building 'C' for final grade. 

(Wall to Wall) Stripped the masking on Building 'B' and started painting the steel on the West side.

(Reliance) Trimed out the Clubhouse.  They worked on moving the fire panel to the Clubhouse.

(SBS) Worked on the punch list for the buildings.

Mario and Juan formed for tomorrows curb and gutter pour.  They added road base and we borrowed DG's jumpping jack to compact it.