Wednesday 7/3/2013

Weather: Partly Cloudy  94˚/62˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (2)
<Reliance>                       (2)

Work in Progress
(Huskies) Used our backhoe to regrade the pad Mario had to make for the painters and rain gutter guys lift on the East end of Building 'C' for final grade. 

(Wall to Wall) Finished painting the steel on Building 'B' and touched up the steel on 'E'.

(Reliance) Trimed out the Clubhouse.  They worked on moving the fire panel to the Clubhouse.  The phone line had not been transferred to the Clubhouse from Building 'A'.  I called Strata and put in an emergency call for no dial tone.  The service tech came out and told Nate (Reliance) that the soonest they could get dial tone would be Friday, due to the holiday.  I called the main office and talked to Valerie,  she checked and told me the same thing.  I called Kristie and warned her that the fire alarm would not call the fire department.  I also called the Marshal and told him. 

We poured the curb and gutter for Building 'B'.  We split it into 2 pours and added retardant but we still had to steal a landscaper to help finish it so we would not loose it.