Tuesday 7/30/2013

Weather: Partly Cloudy 84˚/54˚

Subs on Site:
<Huskies>                        (5)
<Reliance>                       (2)

Work in Progress
(Huskies) Graded and trenched for the strip along the South end of the property.  Started planting trees and plants around Building 'B' and the Southern strip.

(Reliance) Installed the last three light poles.  One is still missing the top and another has been damaged.  They also installed the floodlights for the monument signs.

The remaining items on the temporary C of O were signed off by both the Fire Marshal and the County.  I returned the water meter to Maser.