Weather: Partly Cloudy 92˚/62˚
Subs on Site:
Subs on Site:
<Huskies> (5)
<Wall to Wall> (3)
<Clegg Steel> (3)
<SBS> (1)
<SBS> (1)
Work in Progress
(Huskies) Raked around and installed heads for the ClubHouse. Once again someone has driven over the corners of the grass in Building 'A' parking lot. There were also tire tracks across the North end of Building 'B' to the garage parking lot. Also along 2500 W someone drove over the grass and many sprinkler heads.
(Wall to Wall) Painted the body on the North West corner of Building 'A'.
(Clegg Steel) Installed the last two dumpster gates and cleaned the concrete off of the stairs in each of the Buildings. They did not get all of it cleaned up and Milo (Clegg Steel) told me that if the painters need to clean any more they can back charge them.
(SBS) John Simmons came up to install the interior glass in the ClubHouse and and change out the storage room door for the mechanical room door. The glass he brought up was too small and he could not find the spring hinges for the storage door. He will drive back tomorrow with the right glass.
(SBS) John Simmons came up to install the interior glass in the ClubHouse and and change out the storage room door for the mechanical room door. The glass he brought up was too small and he could not find the spring hinges for the storage door. He will drive back tomorrow with the right glass.