Tuesday 7/9/2013
Weather:
Sunny 92˚/62
˚
Subs on Site
<Huskies> (5)
<Wall to Wall> (4)
<Sterns> (4)
Work in Progress
(Huskies) Prepped for sod around Building 'B' and planted trees in the island against 2500 W.
(Wall to Wall) Building 'A' caulked and prepped.
(Sterns) Poured the last piece of sidewalk behind Building 'C'.