Tuesday 5/15/2012





Weather Sunny 85˚/51˚

Subs on Site
<DG Concrete> (5)

Work in Progress:
Footings for the south half of building 'A' dug, scarified, tested, and failed.  Too wet.  Shad (DG Concrete) and I laid out the north end of Building 'A' so he could dig the footings tonight and let them dry, compact in the morning, and have our retest at noon.

Sewer stared.  The sewer line under main street has a 2" puddle and is not strait. We are on the water table with the sewer on Main Street. Water ran out of the gravel.  Chris (DG Concrete) had to run the sump pump.  The line of the sewer was 25' feet to the east of our first manhole at 235' distance.  Chris (DG Concrete) and I  met on site with Dusty (Maeser) he suggested we set the first run with the smart level and curve it to the manhole.  We checked the slope it is 5.35' fall in 233' run or 2.96%.  Dusty (Maeser) ran and picked up a coupler for the 12" pipe because  the existing lateral had a glue on cap and Dusty (Maeser) did not want the pipe run bell down.  I noticed that the Water lateral is on west side of the sewer line and it is drawn on the east side (The reason for off set manhole problem above).  I called  Lonny (legend) and he will look it over and call me in the morning.  While compacting the sewer trench the ground had a fairly big swell to it.  (DG Concrete) had 13 loads of structural fill delivered today as well as more manhole parts and vaults.








Monday 5/14/2012


 Weather Sunny 81˚/47˚

Subs on Site
<DG Concrete> (5)

Work in Progress:
Chris (DG Concrete) and I laid out the southern half of Building 'A's footings. Sewer pipe and Man holes delivered.  Gravel for sewer bedding delivered.  East  end road graded.  Ben (Horrocks) scheduled to test footings and sewer tomorrow.

Thursday 5/10/2012


 Weather Cloudy 84˚/50˚

Subs on Site
<DG Concrete> (5)

Work in Progress:

Reliance delivered a shipping container on site.  The delivery semi had a hard time with the entrance from 2500 W (we will have to clear out a strait away and blend the elevation change) and had to exit across the field.  I called Travis (Uintah County Roads) about the track-out for Main street.  Travis (Uintah County Roads) said it would be no fee but we need to apply just like on 2500 W and we will have to replace any damaged park strip,walk, or curb.
Chris (DG Concrete) pointed out some evidence of a high water table.  The ground swells in these three locations when the front end loader runs over them
Building 'A' is to grade.  Lonny (Legend) is coming out this weekend to stake out the footings.





Wednesday 5/9/2012




 Weather Cloudy 81˚/47˚

Subs on Site
<DG Concrete> (5)

Work in Progress:
Last night Rulon (Reliance) ran wire to the office trailer and the excavator's RV through a trench the excavators dug with the 'dozer.  (Reliance) will be delivering a storage container on site tomorrow for on site materials.

Road is to rough grade.  2 or 3 different people are hauling dirt off site with there own trucks, which is speeding  the excavation up quite a bit.  Chris (DG Concrete) said sewer pipe should be here this week and manholes on Monday.   Building 'A's footprint and parking lot is to rough grade.  I called Lonny (Legend) to have Building 'A' staked out for start of foundation on Monday.  Lonny (Legend) will come this weekend to stake.

Strata installed INTERNET to the office trailer.

Chris (DG Concrete) and I meet with Ben (Horrocks) so he could get a native proctor.  I sent him the Geotech soils report and a schedule.





















(Pictured left)Proctor Site next to the top manhole

Tuesday 5/8/2012


 Weather Cloudy 74˚/42˚

Subs on Site
<DG Concrete> (5)

Work in Progress:
Met with Gary & Mike (Bandwidth), Terri (Questar), and Travis (Uintah County Roads) about under ground.
Bandwidth wants Strata to run up to the property line with their fiber then stop.  Bandwidth will then follow Rocky Mountain Power's trenches and run to each building.  Bandwidth will supply all the conduit.  Bandwidth requested a single large box on the building for service and 2" conduit (supplied by us) up to  the roof for the future satellite location.  In the unit boxes on the patio/decks they want 2 coax and 2 CAT-5 connected to a punch out box with CAT-5 and coax to each room and the TV room.  Bandwidth would like all CAT-5 terminated with RJ-45 jacks
.
Nick discussed a new layout for Questar to keep them in the park strips as much as possible and also run out to Main street so Questar could have two feeds.   Travis (Uintah County Roads) said there would be a $5,000 fee for cutting the pavement to access the gas line on 2500 West because it is a moratorium road.

Met with Matt (VK Custom Construction/HUD inspector) discussed the retention schedule is 10% up to 50% of the whole project is built then it drops down to 5% until we are 90% complete then it drops to 2.5% until completion.  Set up HUD inspections for the first and third Wednesday of the month at 1:00 PM.  Matt (HUD) needs a spread sheet of stored material with beginning value how much was used and how much remains.  Matt (HUD) would like to have a print out of building progress and labor for the trades.  I am to keep a log book of all progress reports and labor on site as well as the RFI and safety logs.

Monday 5/7/2012



 Weather Cloudy 68˚/40˚

Subs on Site
<DG Concrete> (5)
<Legend Engineering> (1)

Work in Progress:
Jason (Legend Engineering) Shot top back of curb along the road, the corners of building 'A', and top back of curb for building 'A's parking.
DG Concrete continued to cut the road down to sub-grade and ruff cut the grading for the whole site.  They also delivered a dump truck to speed up dirt moving and bring in gravel for the first track out.  They are staying on site in an RV and trailer.

Thursday 5/3/2012

  Weather Cloudy 76˚/51˚

Subs on Site
<DG Concrete> (4)
<Reliance Electrical> (2)

Work in Progress:
Temp power pole set and inspected.  Rocky Mountain Power will activate in 3-5 days.  Rulon will bring temp cord for my trailer on Tuesday.
Trailer delivered and set-up.
Excavator continued cutting the road and doing broad site cutting. They left at 2:30






Wednesday 5/2/2012


 Weather Cloudy 75˚/47˚

Subs on Site
<DG Concrete> (4)
<Legend Engineering> (1)

Work in Progress:
Out-house on site.  Delivery driver hit the fence then backed into the Track-hoe's rolling wheel.
Surveyor Jason (Legend Engineering) on site and started with center of road, sewer, and perimeter of site.  He will not be back until Monday.
Water truck and the rest of silt fence delivered on site.
Sewer stub is 12" and our pipe is 8".  Chris (DG concrete) and Dusty ( Maeser Water) suggest adding a manhole.  Dusty (Maeser Water) said he has a cone section but we would have to supply he box.  Lonny (Legend Engineering) suggested we use 12" pipe to the first manhole instead of adding a new manhole.  Dusty (Maeser Water) said he was OK with that too.
Water stub is 10" our line is 8".  Dusty (Maeser Water) said a reducer is OK. I will email him and get the spec on what he would allow.






Tuesday 5/1/2012


Weather Rain then Sunny 74˚/47˚

Subs on Site
Keith (DG Concrete)  (4)

Work in Progress:

Set up account at Maeser Water for temp water.  They will bill each month and refund the deposit at the end of the job.
Shot elevations on sewer line and reported to Lonny.  Survey tomorrow
Grubbed site. Started removing top soil.
Rulon (Reliance Electric) met with Mike (Strata Networks) about temporary phone.
Mrs Shaw (The Neighbor)came by and was concerned about her fence with the top soil removed. We have left 2-3 feet undisturbed away from her fence.






.

Monday 4/30/2012

Weather Sunny 76˚/49˚

Subs on Site
Keith (DG Concrete)  (3)

Work in Progress:
Pre-Con with Brandon (Maeser Water) got check for temp meter
Keith (DG Concrete) delivered a front end loader.