Wednesday 5/9/2012




 Weather Cloudy 81˚/47˚

Subs on Site
<DG Concrete> (5)

Work in Progress:
Last night Rulon (Reliance) ran wire to the office trailer and the excavator's RV through a trench the excavators dug with the 'dozer.  (Reliance) will be delivering a storage container on site tomorrow for on site materials.

Road is to rough grade.  2 or 3 different people are hauling dirt off site with there own trucks, which is speeding  the excavation up quite a bit.  Chris (DG Concrete) said sewer pipe should be here this week and manholes on Monday.   Building 'A's footprint and parking lot is to rough grade.  I called Lonny (Legend) to have Building 'A' staked out for start of foundation on Monday.  Lonny (Legend) will come this weekend to stake.

Strata installed INTERNET to the office trailer.

Chris (DG Concrete) and I meet with Ben (Horrocks) so he could get a native proctor.  I sent him the Geotech soils report and a schedule.





















(Pictured left)Proctor Site next to the top manhole