Friday 6/8/2012
Weather Sunny & Windy 88˚/53˚
Subs on Site
<Red Oak> (4)
<Legend> (2)
Work in Progress:
(Red Oak) bent the all the bar they had on site into Building 'A's footings. Then they laid out Building 'C's footings
Jason (Legend) replaced grid line F on Building 'C' because the excavator ran it over, double checked the FFE on Building 'A', Finished laying out the water for Building 'A', fixed the size of Building 'A's garage, and gave us center of road with elevations for the fire lane.
Posted by
Charlie Ford
Thursday 6/7/2012

Weather Light Clouds & Windy 85˚/53˚
Subs on Site
<DG Concrete> (6)
<Red Oak Concrete> (8)
Work in Progress:
(DG Concrete) backfilled the water line and started running laterals to the 32 Plexes.
Waylon (Red Oak) started laying out the garage for Building 'A' and discovered that it was dug 5' to wide and 3' too long. I called Jason (Legend) and sent him the pages from my drawings. Jason and Lonny (Legend) discover the drawing they had show the garages larger than the drawing we had.
I called Aaron (Uintah County) and he said their inspection on rebar would be sufficient. We will not need a special inspector for rebar. They would like 24 hour notice on inspection as well as a 2 hour window for inspection before pour.
Posted by
Charlie Ford
Wednesday 6/6/2012
Weather Light Clouds & Windy 63˚/43˚Subs on Site
<DG Concrete> (6)
<Horrocks> (1)
<Red Oak Concrete> (8)
Work in Progress:
Chris (DG Concrete) worked on the water line and reached 2500 W. Dusty (Maeser) brought a single section of 10" pipe because Chris (DG Concrete ran short.
(DG Concrete) installed the fire hydrants and the thrust blocks on each of the joints along the water line. Dusty (Maeser) came out to check on progress and to take pictures of the thrust blocks.
(Red Oak Concrete) arrived on site this morning and started setting footing forms on Building 'A'.Matt (HUD) came by for his bi-weekly meeting. We went over progress and he interviewed two of the excavators.

Posted by
Charlie Ford
Tuesday 6/5/2012
Weather Sunny to Clouds & Windy 89˚/43˚Subs on Site
<DG Concrete> (6)
<Horrocks> (1)
Work in Progress:
Chris (DG Concrete) had to wait for water line parts from Mountain Land so he assemble the joints he did have and the he and Tim (DG Concrete) continued the water line after lunch.
Shad (DG Concrete) Finished Building 'C's foundation and Ben (Horrocks) passed the compaction on the the structural fill, as well as the water line back fill up to the T south of the ClubHouse. Shad (DG Concrete) rough graded the site for Garage 'C'
Bill (EarthTech) approved the 3/8" minus for structural fill. Brad (DG Concrete) started stockpiling the 3/8" sand.
Posted by
Charlie Ford
Monday 6/3/2012

Weather Sunny to Clouds & Windy 91˚/55˚
Subs on Site
<DG Concrete> (6)
<Legend> (2)
Work in Progress:
Jason and Matt (Legend) gave us the remainder of the water line with elevations and locations of the Fire riser in Building 'C'. And corners for rough grade on Buildings 'D' & 'E'
Chris (DG Concrete) laid the water pipe up to Building 'D's Manhole
Tim (DG Concrete) backfilled behind Chris (DG Concrete) on the water line.
Shad (DG Concrete) dug and backfilled more of the footings for Building 'C'. He still has to dig the Eastern wall.
Posted by
Charlie Ford
Friday 6/1/2012
Weather Light Clouds & Windy 85˚/54˚
Subs on Site
<DG Concrete> (7)
<Horrocks> (1)
Work in Progress:
Ben (Horrocks) tested and passed the compaction on the first half of Building 'C's foundation as well as the rest of the sewer line.
Chris (DG Concrete) finished the water line up to the manhole on building 'E'.
Tim (DG Concrete) backfilled the water line after Chris laid it.
Shad (DG Concrete) Continued to dig and backfill Building 'C's foundation

Subs on Site
<DG Concrete> (7)
<Horrocks> (1)
Work in Progress:
Ben (Horrocks) tested and passed the compaction on the first half of Building 'C's foundation as well as the rest of the sewer line.
Chris (DG Concrete) finished the water line up to the manhole on building 'E'.
Tim (DG Concrete) backfilled the water line after Chris laid it.
Shad (DG Concrete) Continued to dig and backfill Building 'C's foundation

Posted by
Charlie Ford
Thursday 5/31/2012
Weather Light Clouds & Windy 80˚/53˚Subs on Site
<DG Concrete> (8)
<Horrocks> (2)
Work in Progress:
Byron (Horrocks), the Soils Engineer, came by to take a look and the site and requested that we send him the report that Bill (EarthTech) will send us regarding their visit on site.
Chris (DG Concrete) continued to work on the waterline. He had to run to Roosevelt for a water pump on the loader. While he was there he picked up some more pipe. Chris (DG Concrete) laid the water line up to the elbow to the Clubhouse.
Shad (DG Concrete) dug and backfilled 50% the foundation for Building 'C'. Then started digging the second half.Tim (DG Concrete) compacted the last of the sewer and backfilled the water trench up to the first manhole.

Posted by
Charlie Ford
Wednesday 5/30/2012
Weather Light Clouds & Windy 80˚/49˚
Subs on Site
<DG Concrete> (8)
<EarthTech> (1)
<Reliance> (1)
Work in Progress:

We meet with Matt (EarthTech) to discuss the structural fill. He gave us three options for eliminating pumping in some locations on site. Matt (EarthTech) also took a sample of the 3/8" material we would like to use under the footings.
Chris (DG Concrete) cut the pad for Building 'B' down to finish floor height with the 'dozer. Water pipe delivered at lunch. Chris (DG Concrete) started the waterline. The stub out from Main Street is 1 foot back behind the sidewalk. Chris (DG Concrete) had to run and buy a sawzall to cut off the glue on cap. He met with Dusty (Maeser) about eliminating some of the smaller angled joints by following the sewer and using 22 1/2˚ joints. Dusty (Maeser) liked that much better. We would be away from the curb in case he had to repair and there would be less joints.
Shad (DG Concrete) dug 33% the footings for Building 'C'.

Tim (DG Concrete) Continued to backfill the sewer with the 3/8" minus fill. All the sewer is filled but still needs the last roll on building 'A' lateral.
(Reliance) brought a truckload of wire to store in the shipping container or Conex Container as they call it. The container is half full already.
Posted by
Charlie Ford
Tuesday 5/29/2012
Weather Sunny & Windy 83˚/48˚
Subs on Site
<DG Concrete> (8)
<Legend> (1)
Work in Progress:
Jason (Legend) surveyed the water line from Main Street to the clubhouse and up to building 'E's manhole. He also gave us grid lines on building 'C' and rough grading corners on Building 'B'.
Shad (DG Concrete) and I laid out 1/2 of Building 'C' and he started digging the footings.
Tim (DG Concrete) continued to backfill the sewer line. He reached the manhole for Building 'D'.Chris (DG Concrete) met with Dusty (Maeser) and tested the sewer line. All passed. I noticed the silt fence was comming up, Chris (DG Concrete) fixed it.
(DG Concrete) added a side dump truck to haul off the clay and bring in structural fill.
Posted by
Charlie Ford
Thursday 5/24/2012

Weather Sunny & Windy 70˚/43˚
Subs on Site
<DG Concrete> (7)
Work in Progress:
Tim (DG Concrete) removed all the mud that was excavated out of the sewer trenches. He then back filled the sewer with the new fill material up to the Clubhouse and then down the main road to Building 'E's man hole.
Shad (DG Concrete) back filled Building 'A's garage footings with the structural fill and compacted them.
Chris (DG Concrete) graded the pad for Building 'C'.
Ben (Horrocks) tested and passed the garage footing compaction as well as the sewer trench. He also got a proctor sample of the new fill material and a sample of the gravel for a possible mixing ratio to get the 5% less material going through the 200 sieve, required for the structural fill under the footings.
(DG Concrete) built an entrance and a ramp onto 2500 W at the southern end of the property for better access to the parking lot and the southern half of the site while the trenches are open.

Posted by
Charlie Ford