Thursday 5/31/2012

Weather Light Clouds & Windy 80˚/53˚


Subs on Site
<DG Concrete> (8)
<Horrocks>       (2)

Work in Progress:
Byron (Horrocks), the Soils Engineer, came by to take a look and the site and requested that we send him the report that Bill (EarthTech) will send us regarding their visit on site.

Chris (DG Concrete) continued to work on the waterline.  He had to run to Roosevelt for a water pump on the loader.  While he was there he picked up some more pipe.  Chris (DG Concrete) laid the water line up to the elbow to the Clubhouse.

Shad (DG Concrete) dug and backfilled 50% the foundation for Building 'C'.  Then started digging the second half.

Tim (DG Concrete) compacted the last of the sewer and backfilled the water trench up to the first manhole.