Weather Sunny & Windy 70˚/43˚
Subs on Site
<DG Concrete> (7)
Work in Progress:
Tim (DG Concrete) removed all the mud that was excavated out of the sewer trenches. He then back filled the sewer with the new fill material up to the Clubhouse and then down the main road to Building 'E's man hole.
Shad (DG Concrete) back filled Building 'A's garage footings with the structural fill and compacted them.
Chris (DG Concrete) graded the pad for Building 'C'.
Ben (Horrocks) tested and passed the garage footing compaction as well as the sewer trench. He also got a proctor sample of the new fill material and a sample of the gravel for a possible mixing ratio to get the 5% less material going through the 200 sieve, required for the structural fill under the footings.
(DG Concrete) built an entrance and a ramp onto 2500 W at the southern end of the property for better access to the parking lot and the southern half of the site while the trenches are open.