Wednesday 6/6/2012


Weather Light Clouds & Windy 63˚/43˚


Subs on Site
<DG Concrete>           (6)
<Horrocks>                 (1)
<Red Oak Concrete>   (8)


Work in Progress:
Chris (DG Concrete) worked on the water line and reached 2500 W.  Dusty (Maeser) brought a single section of 10" pipe because Chris (DG Concrete ran short.

(DG Concrete) installed the fire hydrants and the thrust blocks on each of the joints along the water line.  Dusty (Maeser) came out to check on progress and to take pictures of the thrust blocks.

(Red Oak Concrete)  arrived on site this morning and started setting footing forms on Building 'A'.

Matt (HUD) came by for his bi-weekly meeting.  We went over progress and he interviewed two of the excavators.