Tuesday 5/29/2012


Weather Sunny & Windy 83˚/48˚


Subs on Site
<DG Concrete> (8)
<Legend>          (1)



Work in Progress:
Jason (Legend) surveyed the water line from Main Street to the clubhouse and up to building 'E's manhole.    He also gave us grid lines on building 'C' and rough grading corners on Building 'B'.

Shad (DG Concrete) and I laid out 1/2 of Building 'C' and he started digging the footings.

Tim (DG Concrete) continued to backfill the sewer line.  He reached the manhole for Building 'D'.

Chris (DG Concrete) met with Dusty (Maeser) and tested the sewer line.  All passed.  I noticed the silt fence was comming up, Chris (DG Concrete) fixed it.

(DG Concrete) added a side dump truck to haul off the clay and bring in structural fill.