Wednesday 5/30/2012


Weather Light Clouds & Windy 80˚/49˚


Subs on Site
<DG Concrete> (8)
<EarthTech>      (1)
<Reliance>         (1)

Work in Progress:

We meet with Matt (EarthTech) to discuss the structural fill.  He gave us three options for eliminating pumping in some locations on site.  Matt (EarthTech) also took a sample of the 3/8" material we would like to use under the footings.

Chris (DG Concrete) cut the pad for Building 'B' down to finish floor height with the 'dozer. Water pipe delivered at lunch.  Chris (DG Concrete) started the waterline.  The stub out from Main Street is 1 foot back behind the sidewalk.  Chris (DG Concrete) had to run and buy a sawzall to cut off the glue on cap.  He met with Dusty (Maeser) about eliminating some of the smaller angled joints by following the sewer and using 22 1/2˚ joints.  Dusty (Maeser) liked that much better.  We would be away from the curb in case he had to repair and there would be less joints.

Shad (DG Concrete) dug 33% the footings for Building 'C'.


Tim (DG Concrete) Continued to backfill the sewer with the 3/8" minus fill.  All the sewer is filled but still needs the last roll on building 'A' lateral.

(Reliance) brought a truckload of wire to store in the shipping container or Conex Container as they call it.  The container is half full already.