Tuesday 6/5/2012


Weather Sunny to Clouds & Windy 89˚/43˚


Subs on Site
<DG Concrete> (6)
<Horrocks>       (1)

Work in Progress:
Chris (DG Concrete) had to wait for water line parts from Mountain Land so he assemble the joints he did have and the he and Tim (DG Concrete) continued the water line after lunch.


Shad (DG Concrete) Finished Building 'C's foundation and Ben (Horrocks) passed the compaction on the the structural fill, as well as the water line back fill up to the T south of the ClubHouse.  Shad (DG Concrete) rough graded the site for Garage 'C'

Bill (EarthTech) approved the 3/8" minus for structural fill.  Brad (DG Concrete) started stockpiling the 3/8" sand.