Tuesday 7/9/2013

Weather: Sunny  92˚/62˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Sterns>                          (4)

Work in Progress
(Huskies) Prepped for sod around Building 'B' and planted trees in  the island against 2500 W. 

(Wall to Wall) Building 'A' caulked and prepped.

(Sterns) Poured the last piece of sidewalk behind Building 'C'.




Thursday 7/4/2013

Weather: Partly Cloudy  86˚/63˚

Subs on Site
<Huskies>                        (5)
<Reliance>                       (2)

Work in Progress
(Huskies) Received their sod for the planter against 2500 W and the buildings. 

(Reliance) Worked on odds and ends in the Clubhouse.  Set the light poles outside of the Clubhouse.

Mario cut the control joints into the curb and gutter for Building 'B'.  Then he backfilled for the asphalt patch. 

Wednesday 7/3/2013

Weather: Partly Cloudy  94˚/62˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (2)
<Reliance>                       (2)

Work in Progress
(Huskies) Used our backhoe to regrade the pad Mario had to make for the painters and rain gutter guys lift on the East end of Building 'C' for final grade. 

(Wall to Wall) Finished painting the steel on Building 'B' and touched up the steel on 'E'.

(Reliance) Trimed out the Clubhouse.  They worked on moving the fire panel to the Clubhouse.  The phone line had not been transferred to the Clubhouse from Building 'A'.  I called Strata and put in an emergency call for no dial tone.  The service tech came out and told Nate (Reliance) that the soonest they could get dial tone would be Friday, due to the holiday.  I called the main office and talked to Valerie,  she checked and told me the same thing.  I called Kristie and warned her that the fire alarm would not call the fire department.  I also called the Marshal and told him. 

We poured the curb and gutter for Building 'B'.  We split it into 2 pours and added retardant but we still had to steal a landscaper to help finish it so we would not loose it. 




Tuesday 7/2/2013

Weather: Partly Cloudy  97˚/67˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Reliance>                       (2)
<SBS>                              (1)

Work in Progress
(Huskies) Raked around Building 'C' for final grade. 

(Wall to Wall) Stripped the masking on Building 'B' and started painting the steel on the West side.

(Reliance) Trimed out the Clubhouse.  They worked on moving the fire panel to the Clubhouse.

(SBS) Worked on the punch list for the buildings.

Mario and Juan formed for tomorrows curb and gutter pour.  They added road base and we borrowed DG's jumpping jack to compact it.





Monday 7/1/2013

Weather: Partly Cloudy  100˚/67˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (4)
<Reliance>                       (5)
<SBS>                              (1)
<Sterns>                           (6)

Work in Progress
(Huskies) Hooked up their sprinklers around Building 'B' 

(Wall to Wall) Sprayed the body on Building 'B'.

(Reliance) Trimed out the Clubhouse.

(SBS) Installed the base board and some trim on the Clubhouse.

(Sterns) Poured the first half of the sidewalk behind building 'C'.

Mario dug out the curb and gutter that we need to repour.




.

Friday 6/28/2013

Weather: Partly Cloudy  96˚/60˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)

Work in Progress
(Huskies) Planted sod around Building 'D'.  

(Wall to Wall) Masked Building 'B' trim and painted the trim on the Clubhouse.



.

Thursday 6/27/2013

Weather: Partly Cloudy  101˚/60˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Red Oak>                     (2)

Work in Progress
(Huskies) Planted trees around Building 'A'.  They raked out around Building 'D' & 'E' in preparation of the Sod delivery tomorrow.

(Wall to Wall) Masked Building 'B' and painted the trim.

(Red Oak) Finished the last couple items of trim in the Club House.

Wednesday 6/27/2013

Weather: Partly Cloudy  92˚/55˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Red Oak>                     (4)

Work in Progress
(Huskies) Planted trees around Building 'D' & 'E'.

(Wall to Wall) Prepped the West and North sides of Building 'B'.

(Red Oak) Started installing trim in the Club House.


I met with Jack (Iso Insurance)  he checked each of the fire riser rooms and used the plan cover page for the footage.  He then met with Kristie about the leasing agreements. 

Tuesday 6/25/2013

Weather: Partly Cloudy  85˚/57˚

Subs on Site
<Huskies>                        (5)
<Clegg Steel>                   (4)
<Wall to Wall>                  (3)
<Sterns>                         (4)
<Red Oak>                     (4)

Work in Progress
(Huskies) Worked on final grade and sprinklers around the Clubhouse.  They received their plant delivery for the whole site.

(Clegg Steel) Installed the Dumpster gates and started clean-up of the concrete stairs for paint.

(Wall to Wall) Prepped the East side of Building 'B' there were hundreds of nails in the face of the siding.

(Sterns) Poured a couple loose sidewalk areas that they missed.

(Red Oak) Started installing trim in the Club House.

Mario worked on installing the partitions in the ClubHouse bathrooms.




Monday 6/24/2013

Weather: Partly Cloudy  85˚/54˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Sterns>                         (4)

Work in Progress
(Huskies) Worked on final grade and sprinklers around the Clubhouse.

(Wall to Wall) Prepped the South end of Building 'B' there were hundreds of nails in the face of the siding.

(Sterns) Poured the dumpster pads for 'B' and 'E'.

This weekend while Mario was borrowing the lift to tighten the steel bolts a couple of Sterns employees got in the painters lift and raised it up as high as it would go.  They got locked out of the controls and could not get down,  They called the Fire department but another Sterns employee figured out how to get them down from the bottom controls.  

Mario worked on installing the partitions in the ClubHouse bathrooms.