Thursday 6/27/2013

Weather: Partly Cloudy  101˚/60˚

Subs on Site
<Huskies>                        (5)
<Wall to Wall>                  (3)
<Red Oak>                     (2)

Work in Progress
(Huskies) Planted trees around Building 'A'.  They raked out around Building 'D' & 'E' in preparation of the Sod delivery tomorrow.

(Wall to Wall) Masked Building 'B' and painted the trim.

(Red Oak) Finished the last couple items of trim in the Club House.