Tuesday 6/25/2013

Weather: Partly Cloudy  85˚/57˚

Subs on Site
<Huskies>                        (5)
<Clegg Steel>                   (4)
<Wall to Wall>                  (3)
<Sterns>                         (4)
<Red Oak>                     (4)

Work in Progress
(Huskies) Worked on final grade and sprinklers around the Clubhouse.  They received their plant delivery for the whole site.

(Clegg Steel) Installed the Dumpster gates and started clean-up of the concrete stairs for paint.

(Wall to Wall) Prepped the East side of Building 'B' there were hundreds of nails in the face of the siding.

(Sterns) Poured a couple loose sidewalk areas that they missed.

(Red Oak) Started installing trim in the Club House.

Mario worked on installing the partitions in the ClubHouse bathrooms.