Tuesday 5/14/2013

Weather: Partly Cloudy 84˚/53˚ 

Subs on Site
<Green Clean>                (2)
<Wholesale Flooring>      (3)
<G&M Woods>                 (4)
<Huskies>                        (3)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (4)
<Warburtons>                  (6)
<Clegg Steel>                  (5)
<Air Doctors>                   (4)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Green Clean) Vacuumed and swept Building 'D' and started on Building 'E' windows.

(Wholesale Flooring) Installed the Vinyl in the North Tower of Building 'B'.

(G&M) Started install on the 3rd and 4th floors of South tower in Building 'B'

(Huskies) Installed the sprinklers for Building 'A' and continued trenching around 'D'. 

(Wall to Wall) Continued prep for Building 'C' exterior while they waited for paint delivery.  Bob (Wall to Wall) touched up A103 and A203 patches.

(SBS) Installed base boards on the vinyl in Building 'E'.  Installed hardware in Building 'D'.  They also installed a washer and dryer in A207

(Nutek) Hung the Club House.  Fire taped the garages for 'B' and 'C'. .

(Warburtons) Touched up and replaced trim on Building 'C' where they had left hammer marks.  Worked on the entry on the South East corner of Building 'B'.  

(Clegg Steel) Jack hammered the concrete steps that would not pass inspection.  Rewelded the steel step in Building 'C'.

(Air Doctors) Installed ducts and furnaces in the South Tower Building 'B'. 

(DG Concrete) Graded for sidewalks behind and along Building 'D'.






Monday 5/13/2013

Weather: Partly Cloudy 84˚/53˚ 

Subs on Site
<G&M Woods>                 (4)
<Huskies>                        (3)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (4)
<Warburtons>                  (6)
<Air Doctors>                   (4)
<DG Concrete>                (3)

Work in Progress
(G&M) Stocked all of the Cabinets in Building 'B' and started install.

(Huskies) Finished final grade in front of Building 'C' and started Started trenching around 'D'. 

(Wall to Wall) Delivered a 40' man basket and an 80' man basket lift and started prep on the North side of Building 'C'

(SBS) Installed Thresholds and Knobs in Building 'E'.  Installed hardware in Building 'D'

(Nutek) Hung the Club House.  Fire taped the garages for 'B' and 'C'.  Touched up and finished the texture in Building 'C' patios and breezeways.

(Warburtons) Touched up and replaced trim on Building 'C' where they had left hammer marks.  Worked on the entry on the South East corner of Building 'B'.  Finished the 1:12 cricket on the Club House.  They forgot to bring ther turtle vents and will have to return on Friday to install them.

(Air Doctors) Installed ducts and furnaces in Building 'B'.  Wired up and vented the furnaces in 'D'.

(DG Concrete) Graded for sidewalks behind and along Building 'D'.




Sub Meeting 5/14/2013

Rob (Wall to Wall)
Rick (Warburtons)
Shad (DG Concrete)
Salvador (Huskies)
Jared (Reliance)

Talking Points:
Clean-up: Clean your trash and organize your materials.
Building ‘A’ Patches is A103 and A203 have been textured.  Bob (Wall to Wall) will paint them tomorrow.
Building ‘C’  Re Final on Thursday 5/16.  I have the inspection if anyone needs a list. Paint exterior complete this week.  Rain gutter starts 5/27.  We will build the last rock wall because the lifts will reach from each side.
Building ‘D’  Plumbing finished this week.  Meters set tomorrow morning.  Paint will start 5/20.
Building ‘E’  Carpet scheduled to start Thursday 5/16.  Paint will start 5/23.
Building ‘B’  Cabinets stocked today.  Install starts today as well.  South tower cabinets complete 5/24.  North Tower cabinets complete by 5/30. Grading starts Wednesday 5/15
Club House Drywall starts today.  Hung by Wednesday 5/15.  Taped by Monday 5/20??
 
Schedule:
Building ‘C’
Stairs repourd 5/14
Fire Marshal inspection 5/15
Re Final inspection 5/16
Paint exterior complete 5/17
Building ‘D’
Plumbing complete 5/17
Final inspection 5/23
Building ‘E’
Plumbing complete 5/20
Final inspection 5/23
Building ‘B’
Cabinets stocked 5/13
South Tower Cabinets and Countertops installed 5/24
North Tower Cabinets and Countertops installed 5/29
Club House
Drywall hung 5/15
Tape and texture complete 5/20




Friday 5/10/2013


Weather: Partly Cloudy 71˚/42˚ 

Subs on Site
<Elite Structures>            (2)
<Huskies>                        (3)
<SBS>                              (1)
<Warburtons>                  (6)
<Air Doctors>                    (3)

Work in Progress
(Elite Structures) Installed the panels on Building 'A' carports.

(Huskies) Trenched for irrigation pipes around Building 'C' and started final grade. 

(SBS) Installed knobs and thresholds on Building 'D'.

(Warburtons) Finished siding on Building 'E' entries.  Worked on the patios and breezeway and the North side of Building 'B'. 

(Air Doctors) Hooked up the condensers for Building 'D' and 'E'.  




Thursday 5/9/2013


Weather: Partly Cloudy 69˚/43˚ 

Subs on Site
<Elite Structures>            (2)
<Huskies>                        (3)
<Wall to Wall>                  (3)
<SBS>                              (1)
<Warburtons>                  (6)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Elite Structures) Painted the carports in Building 'A' Parking lot and installed the panels.

(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wall to Wall) Painted 4th floor on Building 'B'. 

(SBS) Installed knobs and thresholds on Building 'D'.

(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the North side of Building 'B'. 

(Air Doctors) Hooked up the condensers for Building 'D' and 'E'.  Installed the Vents out of the chimneys on 'D','E' and 'B'.

(DG Concrete) Installed roof drains on Building 'D' and 'E' and built the last of the rock walls for Building 'D'.




Wednesday 5/8/2013


Weather: Partly Cloudy and windy/Heavy Rain 67˚/44˚ 

Subs on Site
<Elite Structures>            (2)
<Huskies>                        (4)
<Wholesale Flooring        (6)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Warburtons>                  (3)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Elite Structures) Installed the cross beams and prepped for paint in Building 'A' Parking lot.

(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wholesale Flooring) Installed Carpet in Building 'D'.  Laid the last of the carpet in 'C'.  Relaid the carpet in C101 were it had gotten wet.  Repaired the Vinyl in A304's kitchen.

(Wall to Wall) Painted 2nd and 3rd floor on Building 'B' North tower and primed 4th floor.

(SBS) Installed Mirrors and Blinds in Building 'A'.  Thresholds and weather striping in Building 'C'.

(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the North side of Building 'B'. 

(Air Doctors) Installed the last of the condensers for Building 'D' and 'E'.  Started working on the Vents for 'D' and 'E'.

(DG Concrete) Installed the road base for the sidewalks on the West side Building 'E'.   Installed drains in the patios in front of 'D' and 'E'.

Tuesday 5/7/2013

Weather: Partly Cloudy and windy 67˚/44˚ 

Subs on Site
<Huskies>                        (4)
<Wholesale Flooring        (6)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Warburtons>                  (3)
<Red Oak>                       (5)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wholesale Flooring) Installed Vinyl on South Tower Building 'B' and Carpet in Building 'D'.

(Wall to Wall) Primed 2nd and 3rd floor on Building 'B' North tower. 

(SBS) Installed Mirrors and Blinds in Building 'A'.  Thresholds and weather striping in Building 'C' and unboxed the appliances in Buildings 'D' and 'E'.

(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the West side of Building 'B'. 

(Red Oak) Installed trim in Building 'D'.

(Air Doctors) Installed the last of the condensers for Building 'C' and spread the condensers for Building 'D' and 'E'.

(DG Concrete) Installed the road base for the sidewalks in front Building 'E'. Backfilled around the Building.




Monday 5/6/2013

Weather: Partly Cloudy and windy 67˚/44˚ 

Subs on Site
<Huskies>                        (4)
<Wholesale Flooring        (6)
<Sterns>                           (6)
<Nutek>                            (2)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Warburtons>                  (3)
<Red Oak>                       (5)
<DG Concrete>                 (3)

Work in Progress
(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wholesale Flooring) Installed Vinyl on 1st floor Building 'B' and tackstrip in Building 'D'.

(Sterns) Poured sidewalks in front of Building 'D' and the dumpster pad for 'D'.

(Wall to Wall) Painted 4th floor on South tower.  Prepped 2nd and 3rd floor on Building 'B' North tower. 

(SBS) Finished trim on the 4th floor of the North end of Building 'B'. They left to work on Ballard before lunch.

(Nutek)  Taped patios and breezeways on the back side of  Building 'C'.  
(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the West side of Building 'B'. 

(DG Concrete) Installed the road base for the sidewalks in front Building 'E'.  They dug up the meter in front of Building 'E' lowered and installed a 30" meter cans.

I was walking Building 'B' and noticed that the lower stairs felt funny.   I checked all of the lower stairs in Building 'C' and they varied from 7 1/4" to 6 1/4" in height.  I sent Mario to measure the rest of the lower stairs that were poured Thursday in Building 'D', 'E', and 'B'.  'D' may be okay with a variance of 6 5/8" to 7".  Building 'E' varies from 6 1/2" to 7".  Building 'B' varied from 6" - 7" and had some sloped steps.  One step sloped 1 1/4" from front to back.









Thursday 5/3/2013

Weather: Partly Cloudy and windy 56˚/34˚ 

Subs on Site
<Huskies>                        (4)
<Nutek> 
                           (6)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Clegg Steel>                   (6)
<Diamond Z>                    (1)
<Warburtons>                  (10)
<Reliance>                       (2)
<DG Concrete>                 (3)

Work in Progress
(Huskies) Installed final grade around Building 'A'. 

(Wall to Wall) Painted 2nd and 3rd floor on Building 'B' South tower.  When they moved up to paint 4th floor their paint sprayer shorted out and would not spray any more.  They will come at 5 AM Monday and pray the 4th floor so they do not lose schedule.

(SBS) Started trim on the 3rd floor of the North end of Building 'B'. Installed mirrors and blinds on Building 'A'.

(Clegg Steel) poured the stairs pans in 'C','D','E'&'B'. Installed the guardrails on Building 'D' patios.

(Nutek)  Textured on 3rd floor North Tower & taped 4th floor Building 'B'.  Taped patios and breezeways in Building 'E'&'B'.  
.
(Diamond Z) Prepped the dumpster enclosures and poured their grout. 

(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the West side of Building 'B'. 

(Reliance) Finished wiring and passed 4 way on the Club House.

(DG Concrete) Backfilled around Building 'E' the rock walls.  Rebuilt the rock wall behind Building 'C'.  Started grading for sidewalks in front of Building 'D'.





Wednesday 5/1/2013


Weather: Partly Cloudy and windy 57˚/30˚ 

Subs on Site
<Sterns>                           (6)
<Elite Structures>             (2)
<Huskies>                        (4)
<Nutek> 
                           (6)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Diamond Z>                    (3)
<Warburtons>                  (10)
<Reliance>                       (2)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Sterns) Formed the sidewalks in front of Building 'C' and down the road to 'D'.  Strata had installed a pedistall that is only 4' from the curb.  I called Mike (Strata) and they will try to move it tomorrow.

(Elite Structures) Poured the concrete on next 1/2 of the columns.

(Huskies) Laid the irrigation pipes around Building 'A' and started with sections near 'D'. 

(Wall to Wall) Primed 2nd, 3rd, and 4th floor on Building 'B' South tower and then painted 2nd floor.  The Siding guys cut the plastic off the windows.  The painter had to re mask them.

(SBS) Finished trim on the 2nd floor of the North end of Building 'B'. Installed mirrors and blinds on Building 'A'.

(Nutek)  Taped on 3rd & 4th South floor Building 'B'.  Taped patios and breezeways in Building 'E'&'B'
.
(Diamond Z) Finished Building 'B' stone.. And finished the stone around the window wells on Buildings 'D' and 'E'.

(Warburtons) Finsihed all of of Building 'D" except the North entry fascia because the excavator was working there..  Worked on the patios and breezeway and the West side of Building 'B'. 

(Reliance) Finished wiring and passed 4 way on the Club House.

(Air Doctors) Finished a couple of items for the 4 way on the Club House.  Installed condenser on the south side of Building 'C'.   We discovered that the rock wall on the North side of Building 'C' was too close to the building for the condensers to fit. the excavator rebuilt it.

(DG Concrete) Backfilled around Building 'E' the rock walls.  Rebuilt the rock wall behind Building 'C'.  Started grading for sidewalks in front of Building 'D'.