Subs on Site
<Huskies> (4)
<Nutek> (6)
<Wall to Wall> (3)
<SBS> (4)
<Nutek> (6)
<Wall to Wall> (3)
<SBS> (4)
<Clegg Steel> (6)
<Diamond Z> (1)
<Warburtons> (10)
<Reliance> (2)
<DG Concrete> (3)
Work in Progress
(Huskies) Installed final grade around Building 'A'.
(Wall to Wall) Painted 2nd and 3rd floor on Building 'B' South tower. When they moved up to paint 4th floor their paint sprayer shorted out and would not spray any more. They will come at 5 AM Monday and pray the 4th floor so they do not lose schedule.
(SBS) Started trim on the 3rd floor of the North end of Building 'B'. Installed mirrors and blinds on Building 'A'.
(Clegg Steel) poured the stairs pans in 'C','D','E'&'B'. Installed the guardrails on Building 'D' patios.
(Nutek) Textured on 3rd floor North Tower & taped 4th floor Building 'B'. Taped patios and breezeways in Building 'E'&'B'.
.
.
(Diamond Z) Prepped the dumpster enclosures and poured their grout.
(Warburtons) Siding on Building 'E' entries. Worked on the patios and breezeway and the West side of Building 'B'.