Weather: Partly Cloudy and windy 57˚/30˚
Subs on Site
<Sterns> (6)
<Elite Structures> (2)
<Elite Structures> (2)
<Huskies> (4)
<Nutek> (6)
<Wall to Wall> (3)
<SBS> (4)
<Nutek> (6)
<Wall to Wall> (3)
<SBS> (4)
<Diamond Z> (3)
<Warburtons> (10)
<Reliance> (2)
<Air Doctors> (3)
<DG Concrete> (3)
<DG Concrete> (3)
Work in Progress
(Sterns) Formed the sidewalks in front of Building 'C' and down the road to 'D'. Strata had installed a pedistall that is only 4' from the curb. I called Mike (Strata) and they will try to move it tomorrow.
(Elite Structures) Poured the concrete on next 1/2 of the columns.
(Huskies) Laid the irrigation pipes around Building 'A' and started with sections near 'D'.
(Wall to Wall) Primed 2nd, 3rd, and 4th floor on Building 'B' South tower and then painted 2nd floor. The Siding guys cut the plastic off the windows. The painter had to re mask them.
(SBS) Finished trim on the 2nd floor of the North end of Building 'B'. Installed mirrors and blinds on Building 'A'.
(Nutek) Taped on 3rd & 4th South floor Building 'B'. Taped patios and breezeways in Building 'E'&'B'
.
.
(Diamond Z) Finished Building 'B' stone.. And finished the stone around the window wells on Buildings 'D' and 'E'.
(Warburtons) Finsihed all of of Building 'D" except the North entry fascia because the excavator was working there.. Worked on the patios and breezeway and the West side of Building 'B'.
(Reliance) Finished wiring and passed 4 way on the Club House.
(Air Doctors) Finished a couple of items for the 4 way on the Club House. Installed condenser on the south side of Building 'C'. We discovered that the rock wall on the North side of Building 'C' was too close to the building for the condensers to fit. the excavator rebuilt it.
(DG Concrete) Backfilled around Building 'E' the rock walls. Rebuilt the rock wall behind Building 'C'. Started grading for sidewalks in front of Building 'D'.