Monday 5/6/2013

Weather: Partly Cloudy and windy 67˚/44˚ 

Subs on Site
<Huskies>                        (4)
<Wholesale Flooring        (6)
<Sterns>                           (6)
<Nutek>                            (2)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Warburtons>                  (3)
<Red Oak>                       (5)
<DG Concrete>                 (3)

Work in Progress
(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wholesale Flooring) Installed Vinyl on 1st floor Building 'B' and tackstrip in Building 'D'.

(Sterns) Poured sidewalks in front of Building 'D' and the dumpster pad for 'D'.

(Wall to Wall) Painted 4th floor on South tower.  Prepped 2nd and 3rd floor on Building 'B' North tower. 

(SBS) Finished trim on the 4th floor of the North end of Building 'B'. They left to work on Ballard before lunch.

(Nutek)  Taped patios and breezeways on the back side of  Building 'C'.  
(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the West side of Building 'B'. 

(DG Concrete) Installed the road base for the sidewalks in front Building 'E'.  They dug up the meter in front of Building 'E' lowered and installed a 30" meter cans.

I was walking Building 'B' and noticed that the lower stairs felt funny.   I checked all of the lower stairs in Building 'C' and they varied from 7 1/4" to 6 1/4" in height.  I sent Mario to measure the rest of the lower stairs that were poured Thursday in Building 'D', 'E', and 'B'.  'D' may be okay with a variance of 6 5/8" to 7".  Building 'E' varies from 6 1/2" to 7".  Building 'B' varied from 6" - 7" and had some sloped steps.  One step sloped 1 1/4" from front to back.