Monday 5/13/2013

Weather: Partly Cloudy 84˚/53˚ 

Subs on Site
<G&M Woods>                 (4)
<Huskies>                        (3)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Nutek>                            (4)
<Warburtons>                  (6)
<Air Doctors>                   (4)
<DG Concrete>                (3)

Work in Progress
(G&M) Stocked all of the Cabinets in Building 'B' and started install.

(Huskies) Finished final grade in front of Building 'C' and started Started trenching around 'D'. 

(Wall to Wall) Delivered a 40' man basket and an 80' man basket lift and started prep on the North side of Building 'C'

(SBS) Installed Thresholds and Knobs in Building 'E'.  Installed hardware in Building 'D'

(Nutek) Hung the Club House.  Fire taped the garages for 'B' and 'C'.  Touched up and finished the texture in Building 'C' patios and breezeways.

(Warburtons) Touched up and replaced trim on Building 'C' where they had left hammer marks.  Worked on the entry on the South East corner of Building 'B'.  Finished the 1:12 cricket on the Club House.  They forgot to bring ther turtle vents and will have to return on Friday to install them.

(Air Doctors) Installed ducts and furnaces in Building 'B'.  Wired up and vented the furnaces in 'D'.

(DG Concrete) Graded for sidewalks behind and along Building 'D'.




Sub Meeting 5/14/2013

Rob (Wall to Wall)
Rick (Warburtons)
Shad (DG Concrete)
Salvador (Huskies)
Jared (Reliance)

Talking Points:
Clean-up: Clean your trash and organize your materials.
Building ‘A’ Patches is A103 and A203 have been textured.  Bob (Wall to Wall) will paint them tomorrow.
Building ‘C’  Re Final on Thursday 5/16.  I have the inspection if anyone needs a list. Paint exterior complete this week.  Rain gutter starts 5/27.  We will build the last rock wall because the lifts will reach from each side.
Building ‘D’  Plumbing finished this week.  Meters set tomorrow morning.  Paint will start 5/20.
Building ‘E’  Carpet scheduled to start Thursday 5/16.  Paint will start 5/23.
Building ‘B’  Cabinets stocked today.  Install starts today as well.  South tower cabinets complete 5/24.  North Tower cabinets complete by 5/30. Grading starts Wednesday 5/15
Club House Drywall starts today.  Hung by Wednesday 5/15.  Taped by Monday 5/20??
 
Schedule:
Building ‘C’
Stairs repourd 5/14
Fire Marshal inspection 5/15
Re Final inspection 5/16
Paint exterior complete 5/17
Building ‘D’
Plumbing complete 5/17
Final inspection 5/23
Building ‘E’
Plumbing complete 5/20
Final inspection 5/23
Building ‘B’
Cabinets stocked 5/13
South Tower Cabinets and Countertops installed 5/24
North Tower Cabinets and Countertops installed 5/29
Club House
Drywall hung 5/15
Tape and texture complete 5/20