Thursday 5/9/2013


Weather: Partly Cloudy 69˚/43˚ 

Subs on Site
<Elite Structures>            (2)
<Huskies>                        (3)
<Wall to Wall>                  (3)
<SBS>                              (1)
<Warburtons>                  (6)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Elite Structures) Painted the carports in Building 'A' Parking lot and installed the panels.

(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wall to Wall) Painted 4th floor on Building 'B'. 

(SBS) Installed knobs and thresholds on Building 'D'.

(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the North side of Building 'B'. 

(Air Doctors) Hooked up the condensers for Building 'D' and 'E'.  Installed the Vents out of the chimneys on 'D','E' and 'B'.

(DG Concrete) Installed roof drains on Building 'D' and 'E' and built the last of the rock walls for Building 'D'.