Subs on Site
<Green Clean> (2)
<Wholesale Flooring> (3)
<G&M Woods> (4)
<G&M Woods> (4)
<Huskies> (3)
<Wall to Wall> (3)
<SBS> (3)
<SBS> (3)
<Nutek> (4)
<Warburtons> (6)
<Warburtons> (6)
<Clegg Steel> (5)
<Air Doctors> (4)
<Air Doctors> (4)
<Red Oak> (3)
<DG Concrete> (3)
Work in Progress
(Green Clean) Vacuumed and swept Building 'D' and started on Building 'E' windows.
(Wholesale Flooring) Installed the Vinyl in the North Tower of Building 'B'.
(G&M) Started install on the 3rd and 4th floors of South tower in Building 'B'
(Huskies) Installed the sprinklers for Building 'A' and continued trenching around 'D'.
(Wall to Wall) Continued prep for Building 'C' exterior while they waited for paint delivery. Bob (Wall to Wall) touched up A103 and A203 patches.
(G&M) Started install on the 3rd and 4th floors of South tower in Building 'B'
(Huskies) Installed the sprinklers for Building 'A' and continued trenching around 'D'.
(Wall to Wall) Continued prep for Building 'C' exterior while they waited for paint delivery. Bob (Wall to Wall) touched up A103 and A203 patches.
(SBS) Installed base boards on the vinyl in Building 'E'. Installed hardware in Building 'D'. They also installed a washer and dryer in A207
(Nutek) Hung the Club House. Fire taped the garages for 'B' and 'C'. .
(Nutek) Hung the Club House. Fire taped the garages for 'B' and 'C'. .
(Warburtons) Touched up and replaced trim on Building 'C' where they had left hammer marks. Worked on the entry on the South East corner of Building 'B'.
(Clegg Steel) Jack hammered the concrete steps that would not pass inspection. Rewelded the steel step in Building 'C'.
(Air Doctors) Installed ducts and furnaces in the South Tower Building 'B'.
(DG Concrete) Graded for sidewalks behind and along Building 'D'.