Wednesday 5/8/2013


Weather: Partly Cloudy and windy/Heavy Rain 67˚/44˚ 

Subs on Site
<Elite Structures>            (2)
<Huskies>                        (4)
<Wholesale Flooring        (6)
<Wall to Wall>                  (3)
<SBS>                              (4)
<Warburtons>                  (3)
<Air Doctors>                    (3)
<DG Concrete>                 (3)

Work in Progress
(Elite Structures) Installed the cross beams and prepped for paint in Building 'A' Parking lot.

(Huskies) Trenched for irrigation pipes around Building 'C'. 

(Wholesale Flooring) Installed Carpet in Building 'D'.  Laid the last of the carpet in 'C'.  Relaid the carpet in C101 were it had gotten wet.  Repaired the Vinyl in A304's kitchen.

(Wall to Wall) Painted 2nd and 3rd floor on Building 'B' North tower and primed 4th floor.

(SBS) Installed Mirrors and Blinds in Building 'A'.  Thresholds and weather striping in Building 'C'.

(Warburtons) Siding on Building 'E' entries.  Worked on the patios and breezeway and the North side of Building 'B'. 

(Air Doctors) Installed the last of the condensers for Building 'D' and 'E'.  Started working on the Vents for 'D' and 'E'.

(DG Concrete) Installed the road base for the sidewalks on the West side Building 'E'.   Installed drains in the patios in front of 'D' and 'E'.