Friday 7/13/2012


Weather: Partly Cloudy 93˚/59˚

Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (6)

Work in Progress:
I met with Bill (Utah Landscape) we discussed the irrigation plan.   Bill (Utah Landscape) had a couple concerns first was the island in Building 'A's parking lot, the plans show grass and trees and access for irrigation would be hard.  The other concern was, the plan calls for 3' of mulch surrounding each building.    Bill (Utah Landscape) Thinks that will not look very good.



(Red Oak) worked on Building 'C's footings.






500 S progress


(500 South  progress )
We  will be adding utility stubs soon

Thursday 7/12/2012





Weather: Partly Cloudy 94˚/61˚

Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)



Work in Progress:

(Red Oak) Pour the center section of Building 'A' at 4 AM and the breeze ways and patios at 4 PM.

(DG Concrete) compacted all of Building 'D's footings and started digging Building 'E'.  Chris and Tim (DG Concrete) installed the fabric and 8" of sub base for the fire road from 2500 W to the intersection in front of the Club house.

(Reliance) sleeved the road from Building 'D'&'E' to Building 'B' before the road was installed.

Ben (Horrocks) preformed the concrete tests and compaction on Building 'D' the out side walls failed



Wednesday 7/11/2012


 Weather: Sunny 95˚/65˚


Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (5)


Work in Progress:

(Reliance) poured the light poles on the North side of the main road and trenched the conduit between them.

(Red Oak) formed more footings on Building 'C' and poured the North end of Building 'A'

(DG Concrete) dug the remainder of Pond #2 note the standing water in the low end.  Dug Building 'C's footings and added E fill.  They also started on the fabric and the Fire Lane towards the end of the day.







Tuesday 7/10/2012

 Weather: Sunny 95˚/65˚


Subs on Site
<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<Legend>                                     (1)
<DG Concrete>                            (5)

Work in Progress:
(Reliance) dug the light posts on the North side of the road and discovered that one of them landed right on where we had placed a water meter for Building 'B'.

(Red Oak) tied the last of the bar for Building 'A' slab, passed inspection, and poured one end of the Buildings slab.


Cory (Legend) laid out the light pole locations on the  North side of the street for Reliance and then gave Chris (DG Concrete) stakes for the second pond.

(DG Concrete) graded down the breeze ways for our 2" step into the units and added gravel for the patios on Building 'A'.  They also added dirt on the west side of Building 'A' for the parking lot.  Chris(DG Concrete) started digging the second pond.


Monday 7/9/2012


 Weather: Sunny 93˚/60˚


Subs on Site
<Reliance>                                   (3)
<Red Oak>                                  (7)
<Horrocks>                                  (1)
<DG Concrete>                            (5)

Work in Progress:
(Reliance)hooked up the temporary power to the trailer as well as their trailer.  Bryson (Reliance) met
with Mike (Bandwidth) and me about Bandwidth's low voltage requirements.

(Red Oak) laid out the footings for Building 'C' and started forming until the second half of Building 'A's slab was graded, then they tied the bar on the North end, in prep for the inspection and pour tomorrow.

(DG Concrete) cut the rest of the east parking lot for  Building 'A' down to sub grade and grouted the storm drain pipes.



Friday 7/6/2012


Weather: Sunny 86˚/61˚


Subs on Site
<Red Oak>                                  (4)


Work in Progress:
(Red Oak) Pass inspection on Building 'C' garage footing and tied the bar for the slab on Southern half of Building 'A' until they ran out of #3 bar.  #3 bar was delivered this afternoon and the completed the bar and passed inspection.

I met with Mat (HUD) and went over the progress.  He interviewed Nate (Red Oak) who was the only one on site not interviewed.  Nick was called on the phone.

Thursday 7/5/2012


Weather: Sunny 88˚/61˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
 (Reliance) Organized their materials and trailer and worked with Cory(Legend) to layout their transformer locations.

(Red Oak Plumbing)hooked up to the water on the North end and set the tub boxes and floor drains on the whole building.

(Red Oak)Finished tieing the rebar for Building 'C' garage footings and started preping the slab on the Southern half of Building 'A'


(DG Concrete)graded the gravel for the slab on the Southern half of Building 'A'.




Wednesday 7/4/2012


Weather: Sunny 93˚/62˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Red Oak) helped (DG Concrete) layout the interior footings for the southern half of Building 'A'

(Red Oak Plumbing)back fill the portion of the north half of Building 'A' that passed inspection on Tuesday.  They were short on parts to complete and pressure test all of it.

Tuesday 7/3/2012


Weather: Sunny 94˚/59˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Reliance) set up the fax line to the Conex as well as temp power.

(Red Oak Plumbing) readied the underground on the north end of Building 'A' for inspection at the end of the day

(Red Oak) tied bar the the footings of Building 'C' garage.

(DC Concrete) laid more storm drain pipe and started digging Building 'D's footings

Monday 7/2/2012


Weather: Sunny 96˚/58˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (6)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Reliance) Started trenching for the temp power to the trailer and Building 'A'

(Red Oak Plumbing) readied the underground in the first half of Building 'A' for inspection, passed inspection, and back filled the trenches.

(Red Oak)formed the footing in Building 'C' garage footings so the could back fill them to allow accese all around for Building 'C'.

(DG Concrete) back filled the North end of Building 'A' slab, installed strom drain pipe and pressure tested the sewer line from Main St to our first manhole.