Monday 7/9/2012


 Weather: Sunny 93˚/60˚


Subs on Site
<Reliance>                                   (3)
<Red Oak>                                  (7)
<Horrocks>                                  (1)
<DG Concrete>                            (5)

Work in Progress:
(Reliance)hooked up the temporary power to the trailer as well as their trailer.  Bryson (Reliance) met
with Mike (Bandwidth) and me about Bandwidth's low voltage requirements.

(Red Oak) laid out the footings for Building 'C' and started forming until the second half of Building 'A's slab was graded, then they tied the bar on the North end, in prep for the inspection and pour tomorrow.

(DG Concrete) cut the rest of the east parking lot for  Building 'A' down to sub grade and grouted the storm drain pipes.