Monday 7/2/2012


Weather: Sunny 96˚/58˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (6)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Reliance) Started trenching for the temp power to the trailer and Building 'A'

(Red Oak Plumbing) readied the underground in the first half of Building 'A' for inspection, passed inspection, and back filled the trenches.

(Red Oak)formed the footing in Building 'C' garage footings so the could back fill them to allow accese all around for Building 'C'.

(DG Concrete) back filled the North end of Building 'A' slab, installed strom drain pipe and pressure tested the sewer line from Main St to our first manhole.