Tuesday 7/3/2012


Weather: Sunny 94˚/59˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Reliance) set up the fax line to the Conex as well as temp power.

(Red Oak Plumbing) readied the underground on the north end of Building 'A' for inspection at the end of the day

(Red Oak) tied bar the the footings of Building 'C' garage.

(DC Concrete) laid more storm drain pipe and started digging Building 'D's footings