Weather: Sunny 88˚/61˚
Subs on Site
<Reliance> (3)
<Red Oak Plumbing> (2)
<Red Oak> (3)
<DG Concrete> (4)
Work in Progress:
(Reliance) Organized their materials and trailer and worked with Cory(Legend) to layout their transformer locations.
(Red Oak Plumbing)hooked up to the water on the North end and set the tub boxes and floor drains on the whole building.
(Red Oak)Finished tieing the rebar for Building 'C' garage footings and started preping the slab on the Southern half of Building 'A'

(DG Concrete)graded the gravel for the slab on the Southern half of Building 'A'.