Tuesday 7/10/2012

 Weather: Sunny 95˚/65˚


Subs on Site
<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<Legend>                                     (1)
<DG Concrete>                            (5)

Work in Progress:
(Reliance) dug the light posts on the North side of the road and discovered that one of them landed right on where we had placed a water meter for Building 'B'.

(Red Oak) tied the last of the bar for Building 'A' slab, passed inspection, and poured one end of the Buildings slab.


Cory (Legend) laid out the light pole locations on the  North side of the street for Reliance and then gave Chris (DG Concrete) stakes for the second pond.

(DG Concrete) graded down the breeze ways for our 2" step into the units and added gravel for the patios on Building 'A'.  They also added dirt on the west side of Building 'A' for the parking lot.  Chris(DG Concrete) started digging the second pond.