Wednesday 7/11/2012


 Weather: Sunny 95˚/65˚


Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (5)


Work in Progress:

(Reliance) poured the light poles on the North side of the main road and trenched the conduit between them.

(Red Oak) formed more footings on Building 'C' and poured the North end of Building 'A'

(DG Concrete) dug the remainder of Pond #2 note the standing water in the low end.  Dug Building 'C's footings and added E fill.  They also started on the fabric and the Fire Lane towards the end of the day.