Friday 7/6/2012


Weather: Sunny 86˚/61˚


Subs on Site
<Red Oak>                                  (4)


Work in Progress:
(Red Oak) Pass inspection on Building 'C' garage footing and tied the bar for the slab on Southern half of Building 'A' until they ran out of #3 bar.  #3 bar was delivered this afternoon and the completed the bar and passed inspection.

I met with Mat (HUD) and went over the progress.  He interviewed Nate (Red Oak) who was the only one on site not interviewed.  Nick was called on the phone.