Thursday 7/12/2012





Weather: Partly Cloudy 94˚/61˚

Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)



Work in Progress:

(Red Oak) Pour the center section of Building 'A' at 4 AM and the breeze ways and patios at 4 PM.

(DG Concrete) compacted all of Building 'D's footings and started digging Building 'E'.  Chris and Tim (DG Concrete) installed the fabric and 8" of sub base for the fire road from 2500 W to the intersection in front of the Club house.

(Reliance) sleeved the road from Building 'D'&'E' to Building 'B' before the road was installed.

Ben (Horrocks) preformed the concrete tests and compaction on Building 'D' the out side walls failed