
Weather: Partly Cloudy 94˚/61˚
Subs on Site
<Reliance> (2)
<Red Oak> (8)
<Horrocks> (1)
<DG Concrete> (4)
Work in Progress:
(Red Oak) Pour the center section of Building 'A' at 4 AM and the breeze ways and patios at 4 PM.
(DG Concrete) compacted all of Building 'D's footings and started digging Building 'E'. Chris and Tim (DG Concrete) installed the fabric and 8" of sub base for the fire road from 2500 W to the intersection in front of the Club house.

(Reliance) sleeved the road from Building 'D'&'E' to Building 'B' before the road was installed.
Ben (Horrocks) preformed the concrete tests and compaction on Building 'D' the out side walls failed