Friday 8/3/2012


Weather: Partly Cloudy  91˚/54˚

Subs on Site
<Reliance>                    (3)
<Red Oak Plumbing>    (3)
<Red Oak>                    (9)

Work in Progress:
(Reliance) ran conduit to the monument sign location and our primary trench in front of Building 'C' down to the garages.

(Red Oak Plumbing) passed inspection on the underground and back filled his trenches.

(Red Oak) stripped the forms on Building 'D' and started forming footings on Building 'E'.  The E-fill is 4" too  low throughout the whole building.  We checked off all four hubs and the FFE on Building 'D'.

Road Grade

While we had the laser out to check the grading on Building 'E'. I checked the grading on the road just South of the intersection.  The grade called out on the plans slopes up from the West to the East side 6".  When I shot grade from the grade at fabric on the West side to the grade at fabric on the East side

Thursday 8/2/2012



Weather: Partly Cloudy  89˚/55˚

Subs on Site
<Questar>                     (3)
<TouchStone>              (4)
<Reliance>                    (4)
<Red Oak Plumbing>   (3)
<Red Oak>                    (9)
<DG Concrete>            (3)



Work in Progress:
(Questar) ran their main line to 2500 W and installed the 'T' to the feeder right at the asphalt.

(TouchStone)Rolled the joists on the middle section.  They sent the crew home and will bring out new guys next week.

(Reliance) inspected and poured light poles around Building 'C'.  I spoke to Zelph (Reliance) about starting as soon as the floor joist are rolled.  He told me that they would have to wait for the roof before they could pull Romex into the building unless the county signed off on it.

(Red Oak Plumbing) continued to work on the underground for Building 'C'.  They elected to run both sides of the building out on the East end of the Building where the sewer stub is.

(Red Oak) poured the second half of foundation walls for Building 'D' then inspected and poured the Breeze way wall for Building 'D'

(DG Concrete) ran the water meters for Building 'C' so that Ether (Red Oak Plumbing) could hook to them. They also set the irrigation meter for Building 'C's area.  I walked the road with Tim (DG Concrete) to discuss any concerns with the grading and survey.  With the two different types of curb the grading is actually fairly close on the whole road.   The one area of concern was still the South East corner of the intersection, where we already lowered the curb 6".  When Tim (DG Concrete) looked at it we discovered that the road was not graded level in fact it looked to be sloped the wrong way across it.  Tim (DG Concrete) said that with the 6" of adjustment and curb having a 4 7/8" fall to TA they could make it work.

Temp Power:

Zelph (Reliance) and Jake (TouchStone) met together today to arrange the best layout for temp power on Building 'A'.  They looked at TouchStone's air compressors and Zelph will be able to supply sufficient power to each floor and at each end to power it.  We will use the conduit that was erroneously poured into the breeze ways and have an A-frame panel which will feed SO cord up to each floor.


Wednesday 8/1/2012


Weather: Partly Cloudy  87˚/58˚

Subs on Site
<Questar>                 (3)
<TouchStone>           (13)
<Reliance>                 (2)
<Red Oak Plumbing> (3)
<Red Oak>                (9)
<DG Concrete>         (3)


Work in Progress:
(Questar) ran their main line from the intersection up to 2500 S.  They had to go into the parking stalls in front of Building 'D'& 'E'.  I told them they needed 95% compaction on their trenches. I was told that Questar instructed them that we would take care of that.  Two water meter cans got broken in the road near were they worked.  No one noticed doing the damage.  They also went right through the curb and gutter sub base prep on the North West corner near Building 'A'.

(TouchStone) Finished the interiors on the fout Northern units of Building 'A' and Sheeted the Southern end of Building 'A' and started the joist on the middle section.

(Reliance) Inspected and poured 6 more light poles and trenched behind Questar.

(Red Oak Plumbing) Started the underground in Building 'C'

(Red Oak) inspected the foundation walls for Building 'D'  then poured 1/2 and Building 'A' garage walls.  (TouchStone) brought the straps up with them for the HUD meeting.

(DG Concrete) worked on curb and gutter base from the intersection up the garage parking lot on the North side of the road and in front of Building 'D'&'E' on the South side.


Meeting Minutes
With Josh (TouchStone) and Dennis (Ram) both noticed the lack of flow and production with their Framing crew.  They also explained that finding housing was a problem.  They are to going to check around tonight.
Josh (TouchStone) said they would do all they could to get back on schedule.


Tuesday 7/31/2012





Weather: Sunny 88˚/60˚

Subs on Site
<Questar>                (3)
<TouchStone>          (10)
<Reliance>                (2)
<Red Oak>               (9)
<DG Concrete>         (4)

Work in Progress:
(Questar) ran their main line from Main Street North to the club house and started up the main road.  They have to go under the parking because the need 8' set back from the building and do not want to be under the  sidewalk.

(TouchStone) framed interior walls and rolled the floor on the South End of  Building 'A'.



(Reliance) Ran temp power to Building 'A'
(Red Oak)Finished forming the foundation walls for Building 'A' garage and passed inspection, continued forming Building 'D' foundation walls.

(DG Concrete) Backfilled Building 'C' and dug a trench to their trailers for an upgraded power line because  their A/C units were popping the breakers.


Sub Meeting:
(DG Concrete)Curb and gutter is still on schedule. (TouchStone) would like to have the irrigation meter in front of Building 'D' set ASAP so they can have temp water for their trailers.

(Red Oak) will be pouring Building 'A' Garage walls and the first half of Building 'D' walls on Wednesday,  Try for a Thursday pour on the 2nd half.  Then finish the breeze ways on Friday.

Monday 7/30/2012


Weather: Sunny 87˚/63˚

Subs on Site
<TouchStone>          (10)
<Red Oak>               (9)
<DG Concrete>         (4)



Work in Progress:
(TouchStone) framed interior walls and readied for rolling the floor.

(Red Oak) formed the walls for Building 'A' garage laid out the foundation for Building 'D'

(DG Concrete) Back filled the Breeze ways of Building 'C' and moved dirt piles for Questar's (B. Jackson) who got started from Main Street. Shad (DG Concrete) damaged a column. 

Friday 7/27/2012


Weather: Sunny 94˚/67˚

Subs on Site
<TouchStone>          (1)
<Red Oak>               (9)



Work in Progress:
(TouchStone) worked on site clean-up.  All but one of them left last night.  They did not finish the interior walls, the sheeting on the north end of the building, let alone getting the floor rolled.



(Red Oak) passed inspection on the breeze way walls and poured them.  I did not have enough bolts on site for the walls and the columns.  Charlie (Red Oak) had to run and get more bolts from Lowes for me.

(Horrocks) tested the pour.



500 South @ our property




Thursday 7/26/2012


Weather: Sunny 94˚/64˚

Subs on Site
<TouchStone>                             (14)
<Reliance>                                   (2)
<Red Oak>                                  (9)
<Horrocks>                                  (1)
<DG Concrete>                            (3)



Work in Progress:

(TouchStone) Framed the exterior on the North section of  Level 1 on Building 'A' and started building the interiors from the south end.  (TouchStone) delivered a dumpster on site.


(Reliance) Back filled the primary trenches and trenched for their light poles.

(Red Oak) Passed inspection on the East section of Building 'C' and stripped Building 'A' garage footings.  Poured the East end of Building 'C'. (Horrocks) tested it.  After our safety meeting, (Red Oak) tied the top bar on all of Building 'C' and Building 'A' garage to eliminate the stab hazard.

(DG Concrete) graded and prepped the E-fill for curb and gutter for the North East corner of the site and double checked their grading for the rest of the road.  All checked within an inch or two except the squishy section on the South East corner of the intersection.  The grading at that location is 12" below where it should be.  We are checking with the surveyor to see if we can lower the grade in that location so that we will not have to fill the full 12".

Wednesday 7/25/2012


Weather: Partly Cloudy/Slight Rain 87˚/59˚

Subs on Site
<TouchStone>                             (14)
<Reliance>                                   (2)
<Red Oak>                                  (9)
<Horrocks>                                  (1)

<DG Concrete>                            (3)



Work in Progress:

(Touchstone) Framed the exterior on the middle section of  Level 1 on Building 'A'

(Reliance) Inspected and poured 6 more light poles on the East end of the site then back filled the trenches.

(Red Oak) Passed inspection on the center section of Building 'C' as well as Building 'D' footings and poured both.  Then got the East section of Building 'C' ready for inspection tomorrow morning.

(Horrocks) came out to test compaction under Building 'B' footings all passed except one test on the North-East corner.

(DG Concrete) graded all of the parking lot around Building 'A' and finished the E-fill on Building 'B'.  Chris (DG Concrete) started to rough grade the curb on the road on the East end of the site.

Tuesday 7/24/2012



Weather: Partly Cloudy/Slight Rain 85˚/62˚

Subs on Site
<TouchStone>                             (14)
<Reliance>                                  (2)
<Red Oak>                                  (9)
<Horrocks>                                  (1)
<Legend>                                     (1)
<DG Concrete>                            (3)



Work in Progress:                                                                                       
(Touchstone)Started on the exterior walls on the Southern end of Building 'A'.  We discovered some of the nuts for the J bolts were lost.  The bolts and nuts will now be stored under my trailer unless they are being installed.

(Reliance) readied 6 more light poles and trenched the primary to the club house.(Red Oak Plumbing) delivered a truck load of tub/Showers for Building 'A'


(Red Oak) Poured the footings on Building 'D', (Horrocks) took his cyclinders, and (Red Oak) continued to form Building 'C' foundation walls.

(Legend) came out to stake the curb and gutter for all of the East road.

(DG Concrete) graded and compacted the road base for the curb and gutter around Building 'A' and finished digging and adding E Fill to Building 'B' footings.


Sub Meeting:
Chris (DG Concrete)
Bryson (Reliance)
Jake (TouchStone)

Chris (DG Concrete) said he could be finished with base prep for our first half of curb and gutter (Building 'A' and the East Road) by 8/8.  Chris (DG Concrete) and Jake (TouchStone) worked out how to get the lumber to Building 'A' without being in the way of parking lot prep. Chris (DG Concrete) will now be supervising multiple jobs for DG concrete and will not be on site full time.

Bryson (Reliance) will have temp power pulled to Building 'A' by the first of next week.

Jake (TouchStone) said they should have the first floor rolled by the end of this week.  (I called Lenny (Airdoctors) and Ether (Red Oak Plumbing).  Jake (TouchStone) also said they would have the third floor rolled by 8/6 and would need steel for the stairs and roof by then. (Nick sent an email to check Clegg's Steel's progress)











Monday 7/23/2012


Weather: Partly Cloudy 91˚/63˚


Subs on Site
<TouchStone>                             (14)
<Reliance>                                  (2)
<Red Oak>                                  (9)
<Horrocks>                                  (1)
<Legend>                                     (1)
<DG Concrete>                            (2)

Work in Progress:
(Touchstone) Framed and sheeted the party walls as well as the Southern breeze way walls on Building 'A'.  Aaron (Uintah County) was on site after inspecting the foundation walls for Building 'C' so he took a look a the shearwall that runs East and West across the center of Building 'A' because (Touchstone) will be using the double SW-1 vs the single SW-4 method and as such will have to shearwalls face to face.  We are to supply pictures of the second shearwall.

(Reliance) Prepped and Poured 6 light poles on the North East end of the project.  They also hooked up a temp power cord for (TouchStone) to run their air compressor.

(Red Oak) Passed inspection on the East end foundation walls for Building 'C' and poured them.  They also passed inspection on the Footings for Building 'D'

(Horrocks) preformed a concrete test for the East end foundation walls in Building 'C'.

(Legend) gave us the last of the sites light pole locations and corner points for the Clubhouse foundation.

(DG Concrete) Built up the curb and gutter around Building 'A' and added the road base on the East side of Building 'A'.