Friday 7/27/2012


Weather: Sunny 94˚/67˚

Subs on Site
<TouchStone>          (1)
<Red Oak>               (9)



Work in Progress:
(TouchStone) worked on site clean-up.  All but one of them left last night.  They did not finish the interior walls, the sheeting on the north end of the building, let alone getting the floor rolled.



(Red Oak) passed inspection on the breeze way walls and poured them.  I did not have enough bolts on site for the walls and the columns.  Charlie (Red Oak) had to run and get more bolts from Lowes for me.

(Horrocks) tested the pour.



500 South @ our property