Monday 7/23/2012


Weather: Partly Cloudy 91˚/63˚


Subs on Site
<TouchStone>                             (14)
<Reliance>                                  (2)
<Red Oak>                                  (9)
<Horrocks>                                  (1)
<Legend>                                     (1)
<DG Concrete>                            (2)

Work in Progress:
(Touchstone) Framed and sheeted the party walls as well as the Southern breeze way walls on Building 'A'.  Aaron (Uintah County) was on site after inspecting the foundation walls for Building 'C' so he took a look a the shearwall that runs East and West across the center of Building 'A' because (Touchstone) will be using the double SW-1 vs the single SW-4 method and as such will have to shearwalls face to face.  We are to supply pictures of the second shearwall.

(Reliance) Prepped and Poured 6 light poles on the North East end of the project.  They also hooked up a temp power cord for (TouchStone) to run their air compressor.

(Red Oak) Passed inspection on the East end foundation walls for Building 'C' and poured them.  They also passed inspection on the Footings for Building 'D'

(Horrocks) preformed a concrete test for the East end foundation walls in Building 'C'.

(Legend) gave us the last of the sites light pole locations and corner points for the Clubhouse foundation.

(DG Concrete) Built up the curb and gutter around Building 'A' and added the road base on the East side of Building 'A'.