Weather: Partly Cloudy/Slight Rain 85˚/62˚
Subs on Site
<TouchStone> (14)
<Reliance> (2)
<Red Oak> (9)
<Horrocks> (1)
<Legend> (1)
<DG Concrete> (3)
Work in Progress:
(Touchstone)Started on the exterior walls on the Southern end of Building 'A'. We discovered some of the nuts for the J bolts were lost. The bolts and nuts will now be stored under my trailer unless they are being installed.
(Reliance) readied 6 more light poles and trenched the primary to the club house.(Red Oak Plumbing) delivered a truck load of tub/Showers for Building 'A'
(Red Oak) Poured the footings on Building 'D', (Horrocks) took his cyclinders, and (Red Oak) continued to form Building 'C' foundation walls.
(Legend) came out to stake the curb and gutter for all of the East road.
(DG Concrete) graded and compacted the road base for the curb and gutter around Building 'A' and finished digging and adding E Fill to Building 'B' footings.
Sub Meeting:
Chris (DG Concrete)
Bryson (Reliance)
Jake (TouchStone)
Chris (DG Concrete) said he could be finished with base prep for our first half of curb and gutter (Building 'A' and the East Road) by 8/8. Chris (DG Concrete) and Jake (TouchStone) worked out how to get the lumber to Building 'A' without being in the way of parking lot prep. Chris (DG Concrete) will now be supervising multiple jobs for DG concrete and will not be on site full time.
Bryson (Reliance) will have temp power pulled to Building 'A' by the first of next week.
Jake (TouchStone) said they should have the first floor rolled by the end of this week. (I called Lenny (Airdoctors) and Ether (Red Oak Plumbing). Jake (TouchStone) also said they would have the third floor rolled by 8/6 and would need steel for the stairs and roof by then. (Nick sent an email to check Clegg's Steel's progress)