Thursday 7/26/2012


Weather: Sunny 94˚/64˚

Subs on Site
<TouchStone>                             (14)
<Reliance>                                   (2)
<Red Oak>                                  (9)
<Horrocks>                                  (1)
<DG Concrete>                            (3)



Work in Progress:

(TouchStone) Framed the exterior on the North section of  Level 1 on Building 'A' and started building the interiors from the south end.  (TouchStone) delivered a dumpster on site.


(Reliance) Back filled the primary trenches and trenched for their light poles.

(Red Oak) Passed inspection on the East section of Building 'C' and stripped Building 'A' garage footings.  Poured the East end of Building 'C'. (Horrocks) tested it.  After our safety meeting, (Red Oak) tied the top bar on all of Building 'C' and Building 'A' garage to eliminate the stab hazard.

(DG Concrete) graded and prepped the E-fill for curb and gutter for the North East corner of the site and double checked their grading for the rest of the road.  All checked within an inch or two except the squishy section on the South East corner of the intersection.  The grading at that location is 12" below where it should be.  We are checking with the surveyor to see if we can lower the grade in that location so that we will not have to fill the full 12".