Friday 8/3/2012


Weather: Partly Cloudy  91˚/54˚

Subs on Site
<Reliance>                    (3)
<Red Oak Plumbing>    (3)
<Red Oak>                    (9)

Work in Progress:
(Reliance) ran conduit to the monument sign location and our primary trench in front of Building 'C' down to the garages.

(Red Oak Plumbing) passed inspection on the underground and back filled his trenches.

(Red Oak) stripped the forms on Building 'D' and started forming footings on Building 'E'.  The E-fill is 4" too  low throughout the whole building.  We checked off all four hubs and the FFE on Building 'D'.

Road Grade

While we had the laser out to check the grading on Building 'E'. I checked the grading on the road just South of the intersection.  The grade called out on the plans slopes up from the West to the East side 6".  When I shot grade from the grade at fabric on the West side to the grade at fabric on the East side