Thursday 8/2/2012



Weather: Partly Cloudy  89˚/55˚

Subs on Site
<Questar>                     (3)
<TouchStone>              (4)
<Reliance>                    (4)
<Red Oak Plumbing>   (3)
<Red Oak>                    (9)
<DG Concrete>            (3)



Work in Progress:
(Questar) ran their main line to 2500 W and installed the 'T' to the feeder right at the asphalt.

(TouchStone)Rolled the joists on the middle section.  They sent the crew home and will bring out new guys next week.

(Reliance) inspected and poured light poles around Building 'C'.  I spoke to Zelph (Reliance) about starting as soon as the floor joist are rolled.  He told me that they would have to wait for the roof before they could pull Romex into the building unless the county signed off on it.

(Red Oak Plumbing) continued to work on the underground for Building 'C'.  They elected to run both sides of the building out on the East end of the Building where the sewer stub is.

(Red Oak) poured the second half of foundation walls for Building 'D' then inspected and poured the Breeze way wall for Building 'D'

(DG Concrete) ran the water meters for Building 'C' so that Ether (Red Oak Plumbing) could hook to them. They also set the irrigation meter for Building 'C's area.  I walked the road with Tim (DG Concrete) to discuss any concerns with the grading and survey.  With the two different types of curb the grading is actually fairly close on the whole road.   The one area of concern was still the South East corner of the intersection, where we already lowered the curb 6".  When Tim (DG Concrete) looked at it we discovered that the road was not graded level in fact it looked to be sloped the wrong way across it.  Tim (DG Concrete) said that with the 6" of adjustment and curb having a 4 7/8" fall to TA they could make it work.

Temp Power:

Zelph (Reliance) and Jake (TouchStone) met together today to arrange the best layout for temp power on Building 'A'.  They looked at TouchStone's air compressors and Zelph will be able to supply sufficient power to each floor and at each end to power it.  We will use the conduit that was erroneously poured into the breeze ways and have an A-frame panel which will feed SO cord up to each floor.