Subs on Site
<Questar> (3)
<TouchStone> (13)
<Reliance> (2)
<Red Oak Plumbing> (3)
<Red Oak> (9)
<DG Concrete> (3)

(Questar) ran their main line from the intersection up to 2500 S. They had to go into the parking stalls in front of Building 'D'& 'E'. I told them they needed 95% compaction on their trenches. I was told that Questar instructed them that we would take care of that. Two water meter cans got broken in the road near were they worked. No one noticed doing the damage. They also went right through the curb and gutter sub base prep on the North West corner near Building 'A'.
(TouchStone) Finished the interiors on the fout Northern units of Building 'A' and Sheeted the Southern end of Building 'A' and started the joist on the middle section.
(Reliance) Inspected and poured 6 more light poles and trenched behind Questar.
(Red Oak Plumbing) Started the underground in Building 'C'
(Red Oak) inspected the foundation walls for Building 'D' then poured 1/2 and Building 'A' garage walls. (TouchStone) brought the straps up with them for the HUD meeting.
(DG Concrete) worked on curb and gutter base from the intersection up the garage parking lot on the North side of the road and in front of Building 'D'&'E' on the South side.
Meeting Minutes
With Josh (TouchStone) and Dennis (Ram) both noticed the lack of flow and production with their Framing crew. They also explained that finding housing was a problem. They are to going to check around tonight.
Josh (TouchStone) said they would do all they could to get back on schedule.