Weather: Partly Cloudy/Slight Rain 87˚/59˚
Subs on Site
<TouchStone> (14)
<Reliance> (2)
<Red Oak> (9)
<Horrocks> (1)
<DG Concrete> (3)
Work in Progress:
(Touchstone) Framed the exterior on the middle section of Level 1 on Building 'A'
(Reliance) Inspected and poured 6 more light poles on the East end of the site then back filled the trenches.
(Red Oak) Passed inspection on the center section of Building 'C' as well as Building 'D' footings and poured both. Then got the East section of Building 'C' ready for inspection tomorrow morning.
(Horrocks) came out to test compaction under Building 'B' footings all passed except one test on the North-East corner.
(DG Concrete) graded all of the parking lot around Building 'A' and finished the E-fill on Building 'B'. Chris (DG Concrete) started to rough grade the curb on the road on the East end of the site.