Friday 8/31/2012
Weather: Partly Cloudy 84˚/58˚
Subs on Site
<Sterns> (4)
<Red Oak> (6)
<Horrocks> (1)
Work in Progress:
(Sterns)Slipped the last sections of curb
(Red Oak) poured the footings for Building 'B' and the foundation walls on Building 'B' Garage. I ran to Burton Lumber Lindon to pick up the straps for Building 'B' Garage walls and the Club House, then met Charlie (Red Oak) at Fruitland and he took them back.
Posted by
Charlie Ford
Thursday 8/30/2012
Weather: Partly Cloudy 87˚/56˚Subs on Site
<Air Doctors> (3)
<Sterns> (12)
<Red Oak Plumbing> (5)
<Red Oak> (6)
<DG Concrete> (2)
Work in Progress:
(Air Doctors) prepped their holes for exhaust fans and flue pipes. The flue chase walls were not framed on the upper levels so they are limited to what they can do. They parked their trailer between our office trailer and Reliance's office trailer.(Sterns) poured the radius' and augured the areas were they will slip tomorrow on the East side.
(Red Oak Plumbing) prepped and passed inspection on Building 'E' underground. Then back filled.
(Red Oak) got ready for a pour on Building 'B' garage walls but we do not have straps nor a framer to supply them, so they poured Building 'A' Garage floor. They started forming the Club House footings. Th
(DG Concrete) worked with Sterns to install the roof drain pipes were possible and continued with parking sub grade.
Posted by
Charlie Ford
Wednesday 8/29/2012
Weather: Partly Cloudy 88˚/57˚Subs on Site
<Air Doctors> (3)
<Sterns> (12)
<Red Oak Plumbing> (5)
<Red Oak> (6)
<DG Concrete> (2)
Work in Progress:
(Air Doctors)arrived with a camper and we went over their concerns about the plans see RFI #16(Sterns) Continued down the road with curb and gutter pouring their tie ins
(Red Oak Plumbing) Started on underground for Building 'E'
(Red Oak)Finished tieing the bar for Building 'B' footings and started on Building 'B' garage foundation walls.(DG Concrete)Started, at 2500 W, to fill in were needed in the parking areas along the road. Shad (DG Concrete) drove over the valve box for the fire hydrant with the track hoe and broke the 6" line on the hydrant side of the valve. They had it fixed by the end of the day and started a chlorine bake.



Posted by
Charlie Ford
Tuesday 8/28/2012

Weather: Partly Cloudy 88˚/59˚
Subs on Site
<Sterns> (12)
<TouchStone> (16)
<Red Oak> (7)
<DG Concrete> (2)
Work in Progress:
(Sterns) poured the end sections were they could not slip. Including the approaches to 2500 W.(TouchStone) stood some walls on the North end of Building 'A' then cleaned up the area and loaded their campers and left.
(Red Oak) passed inspection for Building 'B' footings and garage foundation walls.

Posted by
Charlie Ford
Monday 8/27/2012

Weather: Partly Cloudy 90˚/59˚
Subs on Site
<Sterns> (12)
<TouchStone> (16)
<Red Oak> (7)
<DG Concrete> (2)
Work in Progress:(Sterns) poured the end sections were they could not slip. Dennis (Sterns) noticed that the large island in Building 'A' parking lot had a transition across the sidewalk, at the handicap ramp on the North end, of 1 foot. I called Lonny (Legend) and we moved the stake in the small parking lot up .8' and the stake out by the road .6'. This will leave a channel in the road.
(TouchStone)Sheeted the 4th Floor
(Red Oak)formed Building 'B' footings.
(DG Concrete) Back filled the interior of Building 'E' and touched up the grades for Sterns
Posted by
Charlie Ford
Friday 8/24/2012
Weather: Sunny 91˚/54˚
Subs on Site
<TouchStone> (14)
<Red Oak> (8)
Work in Progress:
(TouchStone) continued rolling 4th floor joists and started sheeting from both ends

(Red Oak) Poured Building 'D' Floor at 4 AM and continued forming Building 'B' footings
Posted by
Charlie Ford
Thursday 8/23/2012

Weather: Cloudy 82˚/54˚
Subs on Site
<TouchStone> (14)
<Red Oak> (8)
<DG Concrete> (3)
Work in Progress:
(TouchStone) Finished framing the 3nd floor interior bearing walls and started rolling 4th floor joists.(Red Oak) poured Building 'E' walls, and Building 'E' Breeze way walls. Then continued forming Building 'B' footing.
(DG Concrete) Built ramps for the framers on each end of Building 'A'. Graded for sidewalk on Building 'C'. Touched up Building 'B' footing holes for (Red Oak)
Posted by
Charlie Ford
Wednesday 8/22/2012

Weather: Cloudy 81˚/61˚
Subs on Site
<TouchStone> (14)
<Red Oak> (8)
<DG Concrete> (3)
Work in Progress:
(TouchStone) Finished framing the 3nd floor walls.(Red Oak) finished forming Building 'E' Breeze way walls, passed inspection on Building 'E' walls and 'D' floor, and tied bar in Building 'A' garage floor. Then started forming Building 'B' footing
(DG Concrete) Dug the water way in Building 'A' parking lot. Started forming the sidewalk around Building 'C' and compacted the back fill they added around Building 'D'
Terri (Questar) came by and measured the services to the buildings we are going to try and get all off them installed so they do not have to bore under the road. We also drove to 500 South and laid out the two stubs their.
Posted by
Charlie Ford
Tuesday 8/21/2012
Weather: Sunny 90˚/53˚Subs on Site
<TouchStone> (14)
<Red Oak> (7)
<DG Concrete> (2)
Work in Progress:
(TouchStone) Continued framing the 3nd floor walls.
(Red Oak) finished forming the 2nd half of Building 'E' foundation walls
(DG Concrete) re compacted the half of Club house footings that fail the test. and back filled around Buildings 'A', 'C', and 'D'
Steve (Clegg Steel) came out to the site and field measured for the stairs.
Posted by
Charlie Ford
Monday 8/20/2012
Weather: Rain then Sunny 83˚/55˚Subs on Site
<TouchStone> (8)
<Red Oak> (7)
<DG Concrete> (3)
Work in Progress:
(TouchStone) Continued framing the 3nd floor walls.
(Red Oak) Tied Bar in the floor for Building 'D' and started on the 2nd half of Building 'E' walls.
(DG Concrete) Cut Building 'B' parking lot and touched up the curb and gutter grade where Sterns needed.
Posted by
Charlie Ford