Thursday 8/30/2012


Weather: Partly Cloudy  87˚/56˚

Subs on Site
<Air Doctors>              (3)
<Sterns>                      (12)
<Red Oak Plumbing>   (5)
<Red Oak>                  (6)
<DG Concrete>            (2)

Work in Progress:
(Air Doctors) prepped their holes for exhaust fans and flue pipes.  The flue chase walls were not framed on the upper levels so they are limited to what they can do.  They parked their trailer between our office trailer and Reliance's office trailer.

(Sterns) poured the radius' and augured the areas were they will slip tomorrow on the East side.

(Red Oak Plumbing) prepped and passed inspection on Building 'E' underground. Then back filled.

(Red Oak) got ready for a pour on Building 'B' garage walls but we do not have straps nor a framer to supply them, so they poured Building 'A' Garage floor.  They started forming the Club House footings.  Th



(DG Concrete) worked with Sterns to install the roof drain pipes were possible and continued with parking sub grade.